Monetary Cost Estimation

Monte Carlo simulation gives you a probabilistic view of when a project finishes. mcprojsim can extend that same probabilistic reasoning to how much it will cost — turning every iteration's sampled schedule into a cost estimate and surfacing a full cost distribution alongside the duration distribution.

Activating cost estimation

Cost estimation is opt-in: it activates automatically as soon as any cost-related field is present in your project file. Specifically, cost is computed when at least one of the following is set:

Field Where Activates because…
default_hourly_rate > 0 project: section Labor cost is non-zero
hourly_rate (any value) a resources: entry Resource has an explicit rate
fixed_cost a task Task has a fixed fee regardless of duration
cost_impact a risk Risk has a monetary consequence

A default_hourly_rate: 0 alone does not activate cost — zero rate produces zero labor cost, so there is nothing to report. But hourly_rate: 0 on a named resource does activate it (an explicit zero is different from "not set").

Project-level cost fields

Add these to the project: metadata block in your YAML file.

project:
  name: My Project
  start_date: "2026-03-01"
  default_hourly_rate: 150     # fallback rate (per hour) for any task with no resource
  overhead_rate: 0.15          # 15% markup applied to total labor cost
  currency: EUR                # currency code displayed in output (default: EUR)

default_hourly_rate

The hourly rate (in whatever currency you choose) applied to every task that has no named resource, or whose resource has no explicit hourly_rate.

  • Must be ≥ 0
  • If omitted, defaults to 0 (no labor cost for unrated tasks)

overhead_rate

A fractional multiplier added on top of total labour cost to represent management overhead, tooling, office, etc.

overhead = labor_cost × overhead_rate
total_cost = labor_cost + overhead + fixed_costs + risk_cost_impacts
  • Range: 0.03.0 (i.e., up to 300 % markup)
  • Overhead is applied to labor only — fixed costs and risk cost impacts are not marked up again

currency

An arbitrary string label (e.g. EUR, USD, GBP, SEK) displayed next to all cost figures. It is not used for conversion — it is purely cosmetic.

  • If omitted, falls back to the currency setting in your configuration file (default: EUR)

Per-resource hourly rates

When you have named resources, you can assign each a specific rate:

resources:
  - name: alice
    hourly_rate: 240    # senior engineer — overrides the project default
  - name: bob
    hourly_rate: 160    # mid-level engineer
  - name: carol         # no hourly_rate → uses project default_hourly_rate
    experience_level: 1

hourly_rate on a resource overrides default_hourly_rate for tasks assigned to that resource. If a task is assigned to multiple resources the engine uses the mean of their rates as a Phase 1 simplifying assumption (see Known limitations below).

Per-task fixed costs

Some tasks carry a cost regardless of how long they take — a software license, a cloud-infrastructure setup fee, a hardware purchase:

tasks:
  - id: cloud_setup
    name: Cloud Infrastructure Setup
    estimate:
      low: 8
      expected: 16
      high: 30
    fixed_cost: 3500    # flat €3,500 added every iteration, regardless of duration
  • fixed_cost is an unrestricted float — negative values represent credits or rebates (e.g. a committed-spend discount or an early-delivery bonus)
  • Fixed costs are included in total cost but are not subject to overhead_rate

Risk cost impacts

Risks can carry a monetary consequence in addition to (or instead of) a schedule impact. When a risk triggers in an iteration, its cost_impact is added to that iteration's total cost.

risks:
  - name: Vendor support escalation
    probability: 0.25
    impact: 5           # +5 hours schedule impact when triggered
    cost_impact: 4000   # +€4,000 cost impact when triggered
  - name: Early sign-off bonus
    probability: 0.20
    impact: -8          # saves 8 hours
    cost_impact: -1500  # saves €1,500
  - name: Compliance audit fee
    probability: 0.10
    impact: 0           # no schedule impact
    cost_impact: 8000   # pure cost event — affects cost distribution only

Both task-level and project-level risks support cost_impact.

Project-level risks

Project-level risks are defined in a separate project_risks: section at the top level of the YAML file (not nested under project: or tasks:). They apply globally to the whole project:

project_risks:
  - id: funding_delay
    name: Funding approval delay
    probability: 0.15
    impact:
      type: absolute
      value: 80
      unit: hours
    cost_impact: 25000    # resubmission fees + additional consultant time

  - id: vendor_bankruptcy
    name: Key vendor goes bankrupt
    probability: 0.05
    impact: 0              # no schedule impact — cost-only
    cost_impact: 50000     # emergency vendor replacement

Full project example

project:
  name: API Platform
  start_date: "2026-06-01"
  default_hourly_rate: 120
  overhead_rate: 0.18
  currency: EUR

resources:
  - name: alice
    hourly_rate: 200
    experience_level: 3
  - name: bob
    hourly_rate: 140
    experience_level: 2

tasks:
  - id: design
    name: API Design
    estimate: { low: 16, expected: 24, high: 40 }
    resources: [alice]
    risks:
      - name: Scope creep
        probability: 0.30
        impact: 8
        cost_impact: 1500
!!! yaml-cbreak-b5
  - id: backend
    name: Backend Implementation
    estimate: { low: 60, expected: 100, high: 160 }
    dependencies: [design]
    resources: [alice, bob]
    fixed_cost: -2000   # tooling credit

  - id: deploy
    name: Deployment
    estimate: { low: 8, expected: 12, high: 24 }
    dependencies: [backend]
    fixed_cost: 500     # cloud provisioning fee

Running a simulation with cost

# Standard run — cost output appears automatically when cost fields are present
mcprojsim simulate project.yaml

# Set a budget target to see the probability of staying within it
mcprojsim simulate project.yaml --target-budget 40000

# Include full per-task cost breakdown in JSON export
mcprojsim simulate project.yaml -f json --full-cost-detail

Reading cost output

Table mode (default)

┌─────────────────────────────────────────────────────────────┐
│ Cost Distribution (EUR)                                     │
├────────────┬────────────┬────────────┬──────────────────────┤
│ P50        │ P80        │ P90        │ P95                  │
│ €34,200    │ €41,800    │ €46,500    │ €50,100              │
└────────────┴────────────┴────────────┴──────────────────────┘

┌───────────────────────────────────────────────────────────────────┐
│ Budget Analysis                                                   │
├─────────────────────────────────────────────────────────────────── │
│ Target budget:     €40,000                                        │
│ Probability within budget: 74.3%                                  │
│ 80% confidence interval:   €29,800 – €41,800                      │
└───────────────────────────────────────────────────────────────────┘

Plain CLI mode

When no --table flag is used, the cost section is printed in plain text after the standard duration summary, showing the same percentile breakdown plus a brief sensitivity note.

Cost sensitivity

When cost estimation is active, mcprojsim computes a Spearman rank correlation between each task's cost contribution and the total project cost. High-correlation tasks are the biggest cost drivers.

Budget confidence analysis

--target-budget

Pass --target-budget <amount> to see:

  • The probability that total cost stays within the budget
  • The 80 % confidence interval for total cost
mcprojsim simulate project.yaml --target-budget 45000

Programmatic access (Python API)

results = engine.run()

# Probability of finishing within €45,000
p = results.probability_within_budget(45000)

# Budget needed for 90% confidence
budget_90 = results.budget_for_confidence(0.90)

# Confidence interval (point estimate, lower, upper)
point, lo, hi = results.budget_confidence_interval(45000, confidence_level=0.80)

Cost in exported reports

JSON (-f json)

The cost section appears under "cost" in the JSON output:

"cost": {
  "currency": "EUR",
  "mean": 36450.0,
  "std_dev": 6200.0,
  "percentiles": { "50": 35800.0, "80": 41900.0, "90": 46200.0, "95": 49800.0 },
  "overhead_rate": 0.18,
!!! json-cbreak-b5  
  "task_costs": {
    "design": { "mean": 4200.0, "p50": 4050.0, "p90": 5800.0 },
    "backend": { "mean": 28100.0, "p50": 27500.0, "p90": 34200.0 },
    "deploy": { "mean": 3600.0, "p50": 3400.0, "p90": 4800.0 }
  },
  "sensitivity": { "backend": 0.82, "design": 0.35, "deploy": 0.18 },
  "duration_correlation": 0.97
}

Use --full-cost-detail to include the complete per-task breakdown.

CSV (-f csv)

A cost_statistics section is appended at the end of the CSV with one row per percentile plus rows for mean and standard deviation.

HTML (-f html)

The HTML report gains:

  • A Cost Summary card showing mean, median, std dev, and the percentile table
  • A Cost Histogram visualising the cost distribution across iterations
  • A Cost Sensitivity Tornado Chart showing which tasks drive cost variance (Spearman rank correlation, top 15 tasks)
  • A Cost Breakdown by Task table listing each task's mean cost, std dev, min, max, and percentage of total project cost
  • A Budget Confidence card (if --target-budget was provided) with a probability gauge, percentile table, and cost CDF S-curve chart
  • A Cost Sensitivity table ranking tasks by their cost correlation

Configuration defaults

Override cost defaults in a config file so you don't have to repeat them in every project file:

cost:
  default_hourly_rate: 130   # applied when project omits default_hourly_rate
  overhead_rate: 0.10        # default 10% overhead
  currency: EUR              # default currency label
  include_in_output: true    # set false to suppress cost sections globally

include_in_output: false suppresses cost output in all reports and console output, but does not suppress the underlying computation — budget methods on SimulationResults still return values.

Natural-language input

The generate command understands cost fields in plain-text project descriptions. Supported cost-related patterns:

Input pattern Maps to
Default rate: €120/hour, Hourly rate: 150 default_hourly_rate
Overhead: 15%, Overhead rate: 0.15 overhead_rate
Currency: EUR currency
Rate: €200/hour (under a resource) resource hourly_rate
Fixed cost: $5000, One-time cost: 5000 task fixed_cost
Risks: header + structured bullets task risks (see below)
Prose risk sentences task risks with cost_impact

Structured risk format

Indent a Risks: header under a task, then list the risk name, probability, impact, and optional cost impact as sub-bullets:

Task 3: Data Transformation
- Estimate: 40/80/140 hours
- Depends on Task 2
- Risks:
  - Third-Party API Changes
  - Probability: 0.25
  - Impact: 3/5 days
  - Cost impact: 8000

Prose risk format

The parser recognises risk sentences that include a probability and at least one consequence (schedule delay or cost impact). Keywords like penalty, fee, or surcharge produce a positive cost_impact; keywords like bonus, reward, saving, or credit produce a negative cost_impact:

Task 6: Go-Live
- Estimate: 10/20/35 hours
- There is a 25% probability of a deployment rollback penalty of $5000 and 2 days delay
- There is a 15% chance the client rewards early delivery with a $4000 bonus

Full example

Project name: My API
Start date: 2026-06-01
Default rate: €120/hour
Overhead: 15%
Currency: EUR

Resource 1: Alice
- Experience: 3
- Rate: €200/hour
!!! json-cbreak-b5  
Task 1:
- API Design
- Size: M
- Resources: Alice
- Fixed cost: 1000

Task 2:
- Backend
- Size: XL
- Depends on Task 1
- There is a 20% risk of integration delays costing a $3000 fee and adding 2 days
mcprojsim generate project_description.txt > project.yaml
mcprojsim simulate project.yaml --target-budget 50000

See examples/cost_nl_prose_example.txt, examples/cost_nl_example.txt, and examples/cost_nl_risk_example.txt for full natural-language examples with cost and risk definitions.

Secondary currencies and FX conversion

When your team spans multiple countries, or when you report costs to a client in a different currency, mcprojsim can automatically convert every cost distribution to one or more secondary currencies and include the results in all outputs.

How it works

  1. You nominate up to 5 secondary currencies in the project file.
  2. At simulation time, mcprojsim fetches the current mid-market exchange rate from Frankfurter — a free, key-less service backed by official sources.
  3. Rates are cached on disk for 24 hours so that repeated runs do not hit the network (see Rate caching below).
  4. You can optionally mark up the official rate by a conversion cost and an overhead rate to model the real cost of buying foreign currency.
  5. The adjusted rate is applied element-wise to the entire cost distribution — every simulation iteration is converted — so the output is a proper probabilistic distribution in the target currency.

Adjusted-rate formula

r_adj = (1 + fx_conversion_cost + fx_overhead_rate) × r_official
Term Meaning
r_official Mid-market rate fetched from Frankfurter (e.g. 1 EUR = 11.20 SEK)
fx_conversion_cost Bank bid-ask spread as a fraction, e.g. 0.015 = 1.5 %
fx_overhead_rate Additional overhead (hedging, admin) as a fraction, e.g. 0.005 = 0.5 %
r_adj Effective rate actually paid, used for all conversions

Example: EUR → SEK with a 2 % bank spread and 0.5 % admin fee:

r_official = 11.20        # live mid-market
r_adj = (1 + 0.02 + 0.005) × 11.20 = 1.025 × 11.20 = 11.48 SEK/EUR

A project with a P80 cost of €42,000 would show SEK 482,160 at P80.

Project file fields

Add the following to your project: section:

project:
  name: API Platform
  currency: EUR               # primary (base) currency
  default_hourly_rate: 150
  overhead_rate: 0.15

  secondary_currencies: [SEK, USD, GBP]   # up to 5 ISO 4217 codes
  fx_conversion_cost: 0.015               # 1.5% bank spread
  fx_overhead_rate: 0.005                 # 0.5% internal overhead
Field Type Range Default Description
secondary_currencies list of strings up to 5 entries [] ISO 4217 codes to convert to
fx_conversion_cost float 0 – 0.50 0.0 Bank spread fraction
fx_overhead_rate float 0 – 1.0 0.0 Additional overhead fraction
fx_rates mapping any positive float {} Manual rate overrides (bypass live fetch)

All four fields are optional. If secondary_currencies is empty (the default), no FX fetching or conversion is performed.

Manual rate overrides

If you have a contractually locked exchange rate, or simply want reproducible results without a network dependency, set fx_rates to bypass the live fetch:

project:
  currency: EUR
  secondary_currencies: [SEK, USD]
  fx_rates:
    SEK: 11.50    # use this fixed rate — no markups applied
    USD: 1.08     # manual rates are always used as-is

Manual rates take precedence over anything fetched from Frankfurter. No markups are applied to manual rates — they are used exactly as specified.

Suppressing FX at run time

Pass --no-fx to any simulate call to skip secondary-currency output even if the project file defines secondary_currencies:

mcprojsim simulate project.yaml --no-fx

This is useful for quick local runs where network access is unavailable or undesired.

Console output

When secondary currencies are configured, a Cost in Secondary Currencies section is appended after the primary cost table. For each currency it shows:

  • The effective exchange rate used (official and adjusted, if markups were applied)
  • The same confidence-level percentiles as the primary cost table
Cost in Secondary Currencies:
  SEK  1 EUR = 11.48 SEK  (official: 11.20, bank: +1.5%, overhead: +0.5%)
       P50: SEK 391,360  |  P80: SEK 481,160  |  P90: SEK 527,100  |  P95: SEK 563,400

  USD  1 EUR = 1.09 USD  (official: 1.068, bank: +1.5%, overhead: +0.5%)
       P50: $37,200  |  P80: $45,700  |  P90: $50,100  |  P95: $53,500

If the rate source is a manual override, (manual) appears instead of the markup breakdown. If a rate is unavailable (network failure, unknown currency), that currency is silently skipped and a warning is emitted.

FX data in exported reports

JSON (-f json)

A secondary_currencies array is added inside the "cost" section:

"cost": {
  "currency": "EUR",
  "mean": 36450.0,
  "percentiles": { "50": 34200, "80": 41800, "90": 46500, "95": 50100 },
  "secondary_currencies": [
    {
      "currency": "SEK",
      "official_rate": 11.2,
      "adjusted_rate": 11.48,
      "fx_conversion_cost": 0.015,
      "fx_overhead_rate": 0.005,
      "source": "live",
      "fetched_at": "2026-06-01T09:14:33+00:00",
      "mean": 418000.0,
      "percentiles": { "50": 392400, "80": 479700, "90": 533700, "95": 575100 }
    }
  ]
}

The source field is one of "live", "disk_cache", or "manual_override", allowing you to audit which data source was used.

CSV and HTML

Both exporters receive the same fx_provider and include secondary-currency data alongside the primary cost section — extra rows in the CSV cost block and an additional card in the HTML report.

Rate caching

Fetching live rates for every simulation run would be wasteful and fragile. mcprojsim maintains a disk cache at:

~/.mcprojsim/fx_rates_cache.json

Cache behaviour:

Property Value
Location ~/.mcprojsim/fx_rates_cache.json
TTL 24 hours per entry
Granularity Per base-currency / target-currency pair
Format JSON: { "EUR": { "SEK": { "rate": 11.2, "fetched_at": "..." } } }

Entries from different base currencies coexist in the same file. On startup, ExchangeRateProvider loads all fresh entries for the current base currency into memory. Stale entries (older than 24 h) are skipped and re-fetched on next use.

All disk I/O errors (permissions, corrupt file, etc.) are silently swallowed — the cache is best-effort. If the cache cannot be read or written, live rates are still fetched and used for the current run; they just will not be persisted.

Full example with secondary currencies

project:
  name: International API Platform
  start_date: "2026-06-01"
  default_hourly_rate: 150
  overhead_rate: 0.15
  currency: EUR

  # Show costs in Swedish kronor and US dollars as well
  secondary_currencies: [SEK, USD]
  fx_conversion_cost: 0.015   # 1.5% bank spread
  fx_overhead_rate: 0.005     # 0.5% internal admin

resources:
  - name: alice
    hourly_rate: 200
    experience_level: 3
  - name: bob
    hourly_rate: 140
    experience_level: 2

tasks:
  - id: design
    name: API Design
    estimate: { low: 16, expected: 24, high: 40 }
    resources: [alice]

  - id: backend
    name: Backend Implementation
    estimate: { low: 60, expected: 100, high: 160 }
    dependencies: [design]
    resources: [alice, bob]
    fixed_cost: -2000   # tooling credit

  - id: deploy
    name: Deployment
    estimate: { low: 8, expected: 12, high: 24 }
    dependencies: [backend]
    fixed_cost: 500
mcprojsim simulate project.yaml --target-budget 45000

Known limitations

Multi-resource equal-effort-split (Phase 1 simplification)

When a task is assigned to multiple resources, the engine uses the mean of their hourly rates multiplied by the sampled elapsed duration. This assumes each resource contributes an equal share of the effort. If resources truly work in parallel for the full elapsed duration, the actual cost is higher than what the simulation reports.

Example: two resources at €100/hr and €200/hr on a 32-hour task. The engine computes 32 × mean(100, 200) = 32 × 150 = €4,800, which equals the true cost only when each person works 16 hours (equal split). If both work the full 32 hours in parallel the true cost is 32×100 + 32×200 = €9,600.

This limitation will be addressed in a future release with explicit effort tracking per resource.

Example files

File Description
examples/cost_simple.yaml default_hourly_rate + overhead_rate + one fixed_cost + risk cost_impact
examples/cost_constrained.yaml Per-resource rates with resource-constrained scheduling
examples/cost_advanced.yaml Full feature set: per-resource rates, multiple fixed costs and credits, risks with cost-only impacts
examples/cost_nl_example.txt Structured natural-language input with cost fields
examples/cost_nl_prose_example.txt Prose-style natural-language project brief