Getting Started¶
Welcome to the Monte Carlo Project Simulator User Guide.
This short, hands-on chapter is meant to quickly show you mcprojsim in action. If you want a quick, practical tour, follow along: you'll create a sample project file, run a Monte Carlo simulation, and learn how to read the key results and reports. We keep theory to a minimum here — the goal is to spark your curiosity and get you producing real outputs quickly so you can explore the deeper chapters with a bit of context where more advanced concepts are introduced.
What you'll learn¶
- Quick generation of a valid project file from a plain-text description.
- Running a reproducible Monte Carlo simulation and exporting report files.
- Using sensitivity and critical-path outputs to find the tasks that drive schedule risk.
Before you start¶
You need:
- Python 3.13 or newer
- A terminal
pipxfor the easiest CLI install (recommended), orpip
Install Python¶
macOS¶
The recommended way is to use the official installer from python.org. Download the latest macOS package and run it.
Alternatively, use Homebrew:
After installation, verify the version:
Linux¶
Most distributions ship with Python 3 but may not include 3.13 yet. Use your package manager:
Debian / Ubuntu:
Fedora / RHEL:
Arch Linux:
If your distribution's package manager does not offer 3.13 yet, install it from source or use pyenv:
After installation, verify:
If you do not have pipx yet:
Install mcprojsim¶
With pipx (recommended)¶
pipx installs command-line tools in their own isolated virtual environments while still making the command globally available on your PATH. This is important for a tool like mcprojsim for several reasons:
Dependency isolation
pip install drops packages directly into your system or user Python environment. If any dependency conflicts with something already installed — another tool, a framework, or a library your own code depends on — one of them will break silently or produce subtle wrong-version behaviour. pipx eliminates this entirely: every tool lives in its own throwaway environment that no other tool can disrupt.
No accidental breakage of system Python
On macOS and most Linux distributions, the system Python interpreter manages OS-level utilities. Polluting its site-packages with pip install can degrade or break unrelated system tools. pipx never touches the system interpreter.
Easy upgrades and rollbacks
pipx upgrade mcprojsim # upgrade to latest
pipx install mcprojsim==0.10 # pin an exact version
pipx uninstall mcprojsim # clean uninstall, no residue
pip leaves orphaned package files behind on uninstall; pipx removes the entire environment atomically.
Safe alongside virtual environments
If you are already working inside a project venv or a Conda environment, pipx still installs into a separate location. Your project dependencies and the mcprojsim CLI remain fully decoupled.
In summary: use pipx when you want a CLI tool that just works, stays out of your way, and does not drift your Python environment over time.
With pip (if you know what you are doing!)¶
Run mcprojsim using a Docker image from ghcr.io¶
If you prefer not to install Python or want to try mcprojsim without installing, you can run it using the official Docker image.
You can run the image directly with docker run, but it is a bit more complex to set up and use.
In the source distribution there is a helper script mcprojsim.sh that simplifies running the Docker image. It handles mounting the current directory and passing through command-line arguments, so you can use it as if mcprojsim were installed locally. It is available in the bin/ directory of the repository, so you can copy it to a location on your PATH for easy access.
First pull the latest image:
Then you can run mcprojsim commands using the mcprojsim.sh script (just be sure to put it in your PATH or always run it with ./mcprojsim.sh from the directory where it is located). For example, to see the help message:
Verify the installation:¶
or , if you installed with Docker:
Note: You need to add the location of mcprojsim.sh to your PATH or always run it with ./mcprojsim.sh from the directory where it is located
Creating the project specification file¶
Project files describe the project to be simulated and is written in a (fairly) easy to read YAML format. Here we will only touch on the essentials needed to simulate a basic project.
See the Project Files reference for all available fields.
The project file below defines a basic project "Website Refresh" with two tasks where the
second task depends on the first one finishing. Most fields should be easy to understand
but the confidence_levels deserves a closer explanation.
The project simulation results are statistical analysis. This means the result is not single
number when the project is done. Instead the result is a range of numbers with an associated
confidence of success. With the numbers given in the project file the result will be the
50%, 80%, and 90% confidence levels.
project:
name: "Website Refresh"
description: "Small example project"
start_date: "2026-04-01"
confidence_levels: [50, 80, 90]
tasks:
- id: "task_001"
name: "Design updates"
estimate:
low: 2
expected: 3
high: 5
unit: "days"
- id: "task_002"
name: "Frontend changes"
estimate:
low: 4
expected: 6
high: 10
unit: "days"
dependencies: ["task_001"]
uncertainty_factors:
team_experience: "medium"
technical_complexity: "medium"
Generating a YAML project file¶
An alternative way than get all project file details correct is to have mcprojsim generate the YAML projec file for you with the generate command verb. Describe your project in a structured
plain text and let mcprojsim generate command produce the detailed YAML project specification from a less strict textual description of a project.
Create a file named description.txt and write the following (indentation and blank rows has no meaning)
Project name: Website Refresh
Description: Small example project
Start date: 2026-04-01
Task 1:
- Design updates
- Size: S
Task 2:
- Frontend changes
- Depends on Task 1
- Size: M
Generate the project file:
That is it — the generated project.yaml is ready for validation and simulation. You can use T-shirt sizes (XS, S, M, L, XL, XXL), story points, or explicit low/expected/high estimates. See Running Simulations for the full generate command reference.
Flexible input formats
You don't have to use the Task N: header format. The parser also accepts plain numbered lists, bullet lists, and even inline sizes — great for copy-paste from meeting notes or planning tools:
Project name: Website Refresh
Start date: 2026-04-01
1. Design updates [S]
2. Frontend changes (M) depends on Task 1
See Natural Language Input for the full range of supported formats.
Validate the file¶
Before simulating, check the file for errors:
Expected result:
If validation fails, read the reported field name and fix the YAML file before continuing.
Tip: common validation issues are missing id fields on tasks, invalid date formats, or incorrect field names — see Project Files for the full field reference and examples.
Run your first simulation¶
Simulation is done with the simulate command as shown below. The optional flag --seed is used to
specify a seed for the simulation. This is useful to be able to get repeatable results or to see how
specific changes in the project (such as adding risks) alters the result of the simulation
while keeping everything else the same. If no seed is specified an automatic random seed is used.
What this does:
- Runs the default 10 000 Monte Carlo iterations
- Uses
--seed 42so the result is reproducible - Uses
--minimalprints only the most important results to the terminal (try without to get a more extensive output)
Tip: increase precision with --iterations (tradeoff: runtime vs accuracy) and use --seed for reproducible runs; see Running Simulations for full CLI options.
Depending on the version of mcprojsim used the output will look something like the following (numbers will vary by version and platform):
mcprojsim, version 0.15.0
Progress: 100.0% (10000/10000)
=== Simulation Results ===
Project Overview:
Project: Website Refresh
Start Date: 2026-04-01
Number of Tasks: 2
Effective Default Distribution: triangular
T-Shirt Category Used: story
Hours per Day: 8.0
Max Parallel Tasks: 1
Schedule Mode: dependency_only
Calendar Time Statistical Summary:
Mean: 90.65 hours (12 working days)
Median (P50): 89.68 hours
Std Dev: 12.97 hours
Minimum: 55.92 hours
Maximum: 131.62 hours
Project Effort Statistical Summary:
Mean: 90.65 person-hours (12 person-days)
Median (P50): 89.68 person-hours
Std Dev: 12.97 person-hours
Minimum: 55.92 person-hours
Maximum: 131.62 person-hours
Calendar Time Confidence Intervals:
P50: 89.68 hours (12 working days) (2026-04-17)
P80: 102.25 hours (13 working days) (2026-04-20)
P90: 108.53 hours (14 working days) (2026-04-21)
Export results¶
To generate report files, add -f with the desired formats:
If you want to control where the files are written and what base name they use, add -o as well:
This creates files like:
With -o results/website_refresh, the exported files would instead use that path prefix:
The HTML report is the best starting point — open it in your browser:
Tip: export HTML first (-f html) to inspect sensitivity, critical paths, and charts in the rendered report — it is the easiest way to explore results visually.
What the main results mean¶
The output is organised into sections. Here is what each section means:
Project Overview shows that this is a dependency-only simulation (no resource constraints). Max Parallel Tasks is the peak number of tasks that ran in parallel across all iterations.
Calendar Time Statistical Summary describes the elapsed project duration distribution. This is how long the project takes from start to finish on the calendar, based on the 10,000 simulated runs.
Project Effort Statistical Summary describes total person-hours across all tasks. For a single-developer project with sequential tasks the two summaries are identical; they diverge once tasks run in parallel or resources are constrained.
The confidence interval table, like this:
| Percentile | Meaning | Typical use |
|---|---|---|
| P50 | Half of simulated runs finish earlier | Internal discussion target |
| P80 | 80% of runs finish earlier | Common management target |
| P90 | 90% of runs finish earlier | Conservative commitment |
is shown twice — once for calendar time and once for effort — with projected delivery dates (weekends excluded) shown alongside each calendar row.
The other sections in the sample output are worth a quick first-pass explanation too:
- Sensitivity Analysis shows which tasks are most strongly associated with the overall finish date moving later. Higher positive values usually mean those tasks are stronger schedule drivers.
- Schedule Slack shows how much a task can slip before it starts delaying the overall project. A task marked Critical has essentially no slack.
- Most Frequent Critical Paths shows the dependency chains that most often determine the final finish date across the Monte Carlo runs.
- Staffing is an advisory recommendation for team size derived from the simulated effort and parallelism.
At this level, treat these as decision aids:
- percentiles help you choose a date target
- sensitivity helps you see where uncertainty matters most
- critical paths and slack help you see where sequencing risk is concentrated
Useful next commands¶
Run with more iterations for higher precision:
Use a custom configuration file:
Suppress progress output (useful in CI/CD):
Where to go next¶
- Introduction — the ideas behind Monte Carlo project estimation
- Your First Project — build a richer project file step by step
- Task Estimation — T-shirt sizes, story points, and explicit ranges
- Project Files — complete project file reference
- Configuration — customize uncertainty factors and mappings
- Examples — working example projects
- Constrained Scheduling, for modeling resource limits and their impact on schedules
- MCP Server, for AI-assisted project file generation and integration
Try these example projects¶
examples/sample_project.yaml— full sample with risks and resourcesexamples/quickstart_project.yaml— minimal quickstart example used in this chapterexamples/resource_cap_small_task.yaml— a small resource-constrained example to try constrained scheduling