Your first project

This chapter shows how to build a project input file gradually.

The goal is not to start with a large “realistic” file and explain it all at once. Instead, we begin with the smallest useful example and then add one idea at a time: more tasks, dependencies, configuration, uncertainty factors, and risks.

That approach mirrors how most teams actually learn the tool. First they want to know the minimum needed to run a simulation. After that, they want to enrich the model with the information they already have about the work, the team, and the main sources of schedule risk.

The examples in this chapter are intentionally small, but they follow the same style as the more complete files in examples/sample_project.yaml, examples/sample_config.yaml, examples/tshirt_sizing_project.yaml, and examples/story_points_walkthrough_project.yaml.

Chapter outline

In this chapter we will build the input in six stages:

  1. Start with the smallest possible project file.
  2. Add a second task and a dependency.
  3. Introduce a configuration file and uncertainty factors.
  4. Add task-level and project-level risks.
  5. Express work with T-shirt sizes.
  6. Express work with Story Points.

At each step we will run the simulation and look at how the results change.

Quick command and flag map

This chapter focuses on building the project file step-by-step, but it helps to know the full CLI surface area up front.

Commands at a glance

Command Purpose
mcprojsim generate INPUT_FILE Generate a project YAML file from plain-text input
mcprojsim validate PROJECT_FILE Validate a project file without simulating
mcprojsim simulate PROJECT_FILE Run Monte Carlo simulation and optionally export reports
mcprojsim config show Show active configuration

Common simulate flags

Flag What it controls
--iterations, -n Number of Monte Carlo iterations
--seed, -s Reproducibility seed
--config, -c Custom config file
--target-date Probability of finishing on/before a target date
--output-format, -f Export format(s): json, csv, html
--output, -o Export output base path
--critical-paths Number of critical path sequences shown/exported
--table, -t Render CLI tabular sections as ASCII tables
--minimal, -m Minimal console output mode
--verbose, -v Show detailed informational messages
--quiet, -q, -qq Reduce or suppress normal CLI output
--staffing Expanded staffing recommendation tables
--tshirt-category Override default T-shirt category
--velocity-model Override sprint velocity model for how historic data are used (empirical/neg_binomial)
--no-sickness Disable sprint sickness modeling
--two-pass Enable criticality two-pass scheduling (resource-constrained mode)
--pass1-iterations Pass-1 iterations used by --two-pass
--include-historic-base Add Historic Base section/series in HTML+JSON exports

For full details, defaults, and examples, see Running simulations.

This chapter intentionally uses only a small subset of these flags in each step.

The smallest possible project file

The simplest useful project file contains two top-level sections:

  • project: basic metadata about the project.
  • tasks: at least one task with an estimate.

That is enough to validate the file and run a simulation.

Step 1: one task, one estimate

Start with a single task:

project:
  name: "Tiny Landing Page"
  description: "The smallest possible example"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]

tasks:
  - id: "task_001"
    name: "Create landing page"
    estimate:
      low: 2
      expected: 3
      high: 5
      unit: "days"

This file does not yet say anything about dependencies, team characteristics, or risks. It simply says: “we have one task, and we believe it is likely to take around three days, but with some uncertainty around that value”.

Before simulating, it is good practice to validate the file:

mcprojsim validate first-project-step-1.yaml

Expected result:

Validating first-project-step-1.yaml...
✓ Project file is valid!

Now run the simulation:

mcprojsim simulate first-project-step-1.yaml --iterations 5000 --seed 42

Example result summary:

=== Simulation Results ===
Project: Tiny Landing Page
Hours per Day: 8.0
Mean: 42.26 hours (6 working days)
Median (P50): 41.52 hours
Std Dev: 7.93 hours

Confidence Intervals:
  P50: 41.52 hours (6 working days)
  P80: 49.60 hours (7 working days)
  P90: 53.44 hours (7 working days)

The important thing here is not the exact numbers. The important thing is that even a one-task project produces a range of likely outcomes rather than one fixed answer. Results are reported in hours (the canonical internal unit) with working days shown alongside.

Add structure: a second task and a dependency

A one-task example is useful for learning the mechanics, but real projects are interesting because tasks interact. The next step is therefore to add a second task that depends on the first one.

Step 2: sequence the work

project:
  name: "Tiny Landing Page"
  description: "Adding sequencing"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]

tasks:
  - id: "task_001"
    name: "Create landing page"
    estimate:
      low: 2
      expected: 3
      high: 5
      unit: "days"

  - id: "task_002"
    name: "Deploy site"
    estimate:
      low: 1
      expected: 2
      high: 4
      unit: "days"
    dependencies: ["task_001"]

The new information is in the dependencies field. It says that deployment cannot start until the landing page work is complete.

Run it:

mcprojsim simulate first-project-step-2.yaml --iterations 5000 --seed 42

Example result summary:

=== Simulation Results ===
Project: Tiny Landing Page
Hours per Day: 8.0
Mean: 71.58 hours (9 working days)
Median (P50): 71.20 hours
Std Dev: 10.96 hours

Confidence Intervals:
  P50: 71.20 hours (9 working days)
  P80: 80.96 hours (11 working days)
  P90: 86.00 hours (11 working days)

Most Frequent Critical Paths:
  1. task_001 -> task_002 (5000/5000, 100.0%)

Compared with the first example, the schedule is now longer because the project contains more work. More importantly, the dependency means the tasks form a chain rather than happening independently. This is the beginning of a project network.

This is also the point where the input file starts to describe more than estimates. It now describes project structure.

Understanding the critical path output

Starting from this step, the CLI and exports also report full critical path sequences.

That means the tool now shows:

  • task-level criticality, which answers: “how often was this task on a critical path?”
  • full path sequences, which answer: “which complete dependency chains were most often critical?”

For this small example there is only one dependency chain, so the reported path is always:

task_001 -> task_002

In larger projects, several different paths may become critical across the Monte Carlo iterations. The simulator aggregates those paths and shows the most common ones.

You can request more than the default two paths in the CLI:

mcprojsim simulate first-project-step-2.yaml --iterations 5000 --seed 42 --critical-paths 4

And you can control how many are stored and reported by default through config.yaml:

simulation:
  max_stored_critical_paths: 20

output:
  critical_path_report_limit: 2

Add organizational knowledge with a configuration file

So far, the estimates came entirely from the task ranges themselves. In practice, teams usually know more than that. They often know whether the team is experienced, whether the requirements are mature, or whether the technical environment is unusually complex.

In mcprojsim, that sort of shared interpretation belongs in a configuration file.

Step 3: add uncertainty factors

First create a configuration file:

uncertainty_factors:
  team_experience:
    high: 0.90
    medium: 1.0
    low: 1.25

  requirements_maturity:
    high: 1.0
    medium: 1.10
    low: 1.30

  technical_complexity:
    low: 1.0
    medium: 1.15
    high: 1.40

simulation:
  default_iterations: 10000
  random_seed: null

output:
  formats: ["json"]
  include_histogram: true
  histogram_bins: 30

Then add uncertainty-factor labels to the project file:

project:
  name: "Tiny Landing Page"
  description: "Adding uncertainty factors"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]

tasks:
  - id: "task_001"
    name: "Create landing page"
    estimate:
      low: 2
      expected: 3
      high: 5
      unit: "days"
    uncertainty_factors:
      team_experience: "high"
      requirements_maturity: "medium"

  - id: "task_002"
    name: "Deploy site"
    estimate:
      low: 1
      expected: 2
      high: 4
      unit: "days"
    dependencies: ["task_001"]
    uncertainty_factors:
      team_experience: "medium"
      technical_complexity: "medium"

Run it with the configuration file:

mcprojsim simulate first-project-step-3.yaml \
  --config first-project-config.yaml \
  --iterations 5000 \
  --seed 42

Example result summary:

=== Simulation Results ===
Project: Tiny Landing Page
Hours per Day: 8.0
Mean: 53.76 hours (7 working days)
Median (P50): 53.44 hours
Std Dev: 8.32 hours

Confidence Intervals:
  P50: 53.44 hours (7 working days)
  P80: 60.88 hours (8 working days)
  P90: 64.64 hours (9 working days)

This is an important modeling step.

The project file still contains the project-specific facts: tasks, estimates, and dependencies. The configuration file now contains the organization’s shared interpretation of labels such as high team_experience or medium technical_complexity.

In this example, the overall forecast becomes shorter than in Step 2 because the chosen factors make part of the work more favorable than the neutral baseline.

If you want to inspect the active merged configuration (built-in defaults plus any custom overrides), run:

mcprojsim config show --config-file first-project-config.yaml

Add explicit risk events

Uncertainty factors model persistent conditions around the work. Risks model events that may or may not happen.

That distinction matters. A distributed team is not an event; it is a condition. A late stakeholder change is an event; it may happen, or it may not.

Step 4: add project-level and task-level risks

project:
  name: "Tiny Landing Page"
  description: "Adding risk events"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]
project_risks:
  - id: "risk_001"
    name: "Late stakeholder changes"
    probability: 0.20
    impact:
      type: "absolute"
      value: 2
      unit: "days"
tasks:
  - id: "task_001"
    name: "Create landing page"
    estimate:
      low: 2
      expected: 3
      high: 5
      unit: "days"
    uncertainty_factors:
      team_experience: "high"
      requirements_maturity: "medium"
  - id: "task_002"
    name: "Deploy site"
    estimate:
      low: 1
      expected: 2
      high: 4
      unit: "days"
    dependencies: ["task_001"]
    uncertainty_factors:
      team_experience: "medium"
      technical_complexity: "medium"
    risks:
      - id: "risk_002"
        name: "Hosting problem"
        probability: 0.15
        impact: 1.5

Run it:

mcprojsim simulate first-project-step-4.yaml \
  --config first-project-config.yaml \
  --iterations 5000 \
  --seed 42

Example result summary:

=== Simulation Results ===
Project: Tiny Landing Page
Hours per Day: 8.0
Mean: 58.88 hours (8 working days)
Median (P50): 58.00 hours
Std Dev: 11.36 hours

Confidence Intervals:
  P50: 58.00 hours (8 working days)
  P80: 68.56 hours (9 working days)
  P90: 74.32 hours (10 working days)

Notice what happened relative to Step 3:

  • the mean increased,
  • the upper percentiles increased,
  • the spread increased.

That is exactly what we expect when we add plausible delay events to the model. The file is not just more detailed. It is representing more of the actual uncertainty that the team believes exists.

An alternative style: T-shirt sized estimates

So far, every task has used an explicit estimate range with low, expected, and high. That is often the best choice when the team is comfortable expressing estimates directly in days.

However, some teams think more naturally in relative sizing. They can say that one task is S, another is M, and another is XL, even when they do not yet want to commit to detailed numeric ranges.

mcprojsim supports that style directly.

Step 5: use t_shirt_size instead of explicit ranges

In the source code, a task estimate may specify t_shirt_size instead of expected and the related range values. Validation accepts that form, and the simulation engine later resolves the symbolic size to concrete low, expected, and high values from the active configuration.

That means a T-shirt-sized task still becomes an ordinary probabilistic range during simulation. The symbolic label is just a more convenient way to express the estimate in the input file.

Important: T-shirt size estimates must not include a unit field in the project file. The unit is determined by the configuration file's t_shirt_size_unit setting (default: "hours").

Here is a small example:

project:
  name: "Tiny Landing Page"
  description: "T-shirt sizing example"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]
tasks:
  - id: "task_001"
    name: "Design page"
    estimate:
      t_shirt_size: "S"
    dependencies: []
    uncertainty_factors:
      team_experience: "high"
      requirements_maturity: "high"
  - id: "task_002"
    name: "Build page"
    estimate:
      t_shirt_size: "M"
    dependencies: ["task_001"]
    uncertainty_factors:
      team_experience: "medium"
      technical_complexity: "medium"
  - id: "task_003"
    name: "Deploy page"
    estimate:
      t_shirt_size: "XS"
    dependencies: ["task_002"]

Note that no unit field appears on any task — the unit is taken from the configuration.

The same example is also available as examples/tshirt_walkthrough_project.yaml, with a matching configuration file at examples/tshirt_walkthrough_config.yaml.

How T-shirt sizes are configured

If you want to use a custom configuration file with T-shirt estimates, add a t_shirt_sizes section like this:

t_shirt_sizes:
  story:
    XS:
      low: 3
      expected: 5
      high: 15
    S:
      low: 5
      expected: 16
      high: 40
    M:
      low: 40
      expected: 60
      high: 120

t_shirt_size_default_category: story

The application ships with built-in mappings for multiple categories (bug, story, epic, business, initiative) and defaults bare sizes like M to the epic category. In this example, t_shirt_size_default_category: story makes bare sizes use story-scale values instead.

If you use your own configuration file, it is merged onto built-in defaults. That means you do not need to redefine t_shirt_sizes unless you want to override defaults.

The simulation engine resolves each T-shirt label against the active merged configuration and raises an error only when the requested category/size is unknown.

This detail is important: t_shirt_size is not just a comment or a reporting label. It is a real input that must be backed by a configuration mapping.

In other words, you have two common options:

  • run without --config and use built-in size mappings, or
  • run with --config to override only the categories/sizes you want to change.

Run the T-shirt-sized example like this:

mcprojsim simulate examples/tshirt_walkthrough_project.yaml \
  --config examples/tshirt_walkthrough_config.yaml \
  --iterations 5000 \
  --seed 42

Example result summary:

=== Simulation Results ===
Project: Tiny Landing Page
Hours per Day: 8.0
Mean: 11.46 hours (2 working days)
Median (P50): 11.37 hours
Std Dev: 1.63 hours

Confidence Intervals:
  P50: 11.37 hours (2 working days)
  P80: 12.87 hours (2 working days)
  P90: 13.67 hours (2 working days)

The interpretation is exactly the same as for explicit ranges. The only difference is how the task effort was expressed in the input file.

T-shirt sizes are especially useful early in planning, when the team can compare tasks relative to each other more easily than they can assign precise numeric ranges. Later, if needed, the team can replace those symbolic sizes with explicit estimate ranges for finer control.

Another alternative style: Story Point estimates

Some teams prefer to estimate backlog items in Story Points rather than T-shirt sizes or explicit day ranges.

mcprojsim supports that style as another symbolic estimate form. In the input file you provide a story_points value, and during simulation the active configuration resolves it to a numeric (low, expected, high) range in the configured unit (default: days).

Important: Story point estimates must not include a unit field in the project file. The unit is determined by the configuration file's story_point_unit setting (default: "days").

Step 6: use story_points

Here is a small Story Point example:

project:
  name: "Tiny Landing Page"
  description: "Story Point sizing example"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]
tasks:
  - id: "task_001"
    name: "Design page"
    estimate:
      story_points: 2
    dependencies: []

  - id: "task_002"
    name: "Build page"
    estimate:
      story_points: 5
    dependencies: ["task_001"]

  - id: "task_003"
    name: "Deploy page"
    estimate:
      story_points: 1
    dependencies: ["task_002"]

Note that no unit field appears on any task — the unit is taken from the configuration.

The same example is also available as examples/story_points_walkthrough_project.yaml, with a matching configuration file at examples/story_points_walkthrough_config.yaml.

How Story Points are configured

If you want to customize Story Point mappings, add a story_points section to the configuration file:

story_points:
  1:
    low: 0.5
    expected: 1
    high: 3
  2:
    low: 1
    expected: 2
    high: 4
  3:
    low: 1.5
    expected: 3
    high: 5
  5:
    low: 3
    expected: 5
    high: 8
  8:
    low: 5
    expected: 8
    high: 15

These are built-in defaults. If you provide a custom configuration file, you may override only the Story Point values you want to recalibrate for your team; the remaining built-in defaults stay available.

As with T-shirt sizes, a custom config file does not need to redefine story_points unless you are changing them.

Run the Story Point example like this:

mcprojsim simulate examples/story_points_walkthrough_project.yaml \
  --config examples/story_points_walkthrough_config.yaml \
  --iterations 5000 \
  --seed 42

Story Points are useful when the team has a stable internal understanding of what 1, 2, 3, 5, or 8 mean, but that understanding does not translate directly to raw hours or days. The config file is where that team-specific calibration belongs.

What each stage added

It is useful to summarize what changed at each step:

Step New concept Why it matters
1 Single task with a range estimate Gives the smallest valid simulation input
2 Dependencies Turns isolated tasks into a schedule network
3 Configuration and uncertainty factors Adds team and context knowledge without cluttering the project file
4 Risks Models probabilistic events that may push the schedule later
5 T-shirt sizes Lets teams express effort symbolically while still simulating numeric ranges
6 Story Points Lets agile teams use calibrated relative sizing while still simulating numeric ranges

This is a good way to think about building real project files. Start with the structure that is definitely known. Then add more realism in layers.

A practical workflow for real projects

When building your own project file, the following sequence usually works well:

  1. List the tasks.
  2. Add simple effort ranges.
  3. Add dependencies.
  4. Validate the file.
  5. Run an initial simulation.
  6. Add uncertainty factors from a shared configuration file.
  7. Add the most important task-level and project-level risks.
  8. Re-run the simulation and compare the percentiles.

This approach helps prevent over-modeling too early. A simple, valid project file that you understand is more useful than a large, complicated file that nobody fully trusts.

How this chapter connects to the shipped examples

The tiny examples in this chapter are teaching examples. The files in the examples/ directory show how the same ideas scale up.

  • examples/sample_project.yaml shows a more complete project with several tasks, dependencies, uncertainty factors, and risks.
  • examples/sample_config.yaml shows a fuller configuration with reusable uncertainty-factor mappings and output settings.
  • examples/tshirt_sizing_project.yaml shows an alternative style where tasks use T-shirt sizes instead of explicit low, expected, and high values.
  • examples/story_points_walkthrough_project.yaml shows the same symbolic-estimate idea using Story Points and a configuration mapping.
  • examples/project_with_custom_thresholds.yaml shows how project-level reporting thresholds can be tuned for stricter or more conservative decision-making.

If you have understood the stages in this chapter, those larger example files should now feel much easier to read.

What to try next

Once you are comfortable with the basic structure, good next experiments are:

  • change a dependency and see how the forecast moves,
  • add a task-level risk and compare P80 or P90,
  • move uncertainty-factor labels from one level to another,
  • try T-shirt sizes instead of explicit estimate ranges,
  • try Story Points with a team-calibrated config mapping,
  • export JSON or HTML output and inspect the richer reports.

The next chapters go deeper into the input format and configuration options. The purpose of this chapter was simply to get you from “empty file” to “first useful simulation” in a gradual and understandable way.

\newpage