Task Estimation¶
This chapter explains how individual tasks are estimated in mcprojsim and how those estimates drive the Monte Carlo simulation. Every task in a project file needs an effort estimate. That estimate is not a single fixed number — it is a structured description of plausible effort that the simulator samples from in each iteration.
The goal of this chapter is to explain all supported estimation methods, the probability distributions behind them, and how to specify each one in a project file.
How estimation works in the simulation¶
In each Monte Carlo iteration, the simulator processes every task as follows:
- Read the estimate from the task definition.
- Resolve symbolic estimates (T-shirt sizes or story points) into numeric ranges using the configuration file.
- Sample a base duration from the specified probability distribution.
- Apply uncertainty factors (multiplicative adjustment).
- Evaluate task-level risks (additive impact if triggered).
The result is the task's effective duration for that iteration. Over thousands of iterations, the sampled values form a distribution that captures the inherent uncertainty in the estimate.
This chapter focuses on steps 1 through 3. Uncertainty factors and risks are covered in Uncertainty Factors and Risks.
Estimation methods at a glance¶
mcprojsim supports four ways to express task effort. Each method provides the same information to the simulator — a probability distribution to sample from — but is suited to different estimation contexts.
| Method | Input | Resolved to | Best for |
|---|---|---|---|
| Explicit range (triangular) | low, expected, high |
Used directly | Teams comfortable giving numeric estimates with bounded outcomes |
| Explicit range (log-normal) | low, expected, high, distribution: "lognormal" |
Used directly | Tasks with significant right-tail risk or open-ended uncertainty |
| T-shirt size | t_shirt_size (e.g., "M" or "epic.M") |
Looked up in config → low, expected, high |
Early-stage or relative estimation |
| Story points | story_points (e.g., 5) |
Looked up in config → low, expected, high |
Teams using story point estimation practices |
All four methods ultimately feed into the same simulation machinery. T-shirt sizes and story points are convenience mappings that resolve to explicit ranges before sampling begins.
Accepted field aliases¶
For explicit ranges, the estimate model accepts these equivalent field names:
| Canonical field | Accepted alias |
|---|---|
low |
min |
expected |
most_likely |
high |
max |
You can use either form in YAML or TOML. They are interpreted identically.
Explicit range estimates¶
The most direct way to estimate a task is to provide three values that describe the range of plausible effort:
| Parameter | Meaning | Required |
|---|---|---|
low |
The shortest plausible duration (optimistic) | Yes |
expected |
The expected duration under normal conditions | Yes |
high |
The longest plausible duration (pessimistic) | Yes |
unit |
The time unit: "hours", "days", or "weeks" (default: "hours") |
No |
The three values must satisfy: low ≤ expected ≤ high.
Basic example¶
tasks:
- id: "task_001"
name: "Database schema design"
estimate:
low: 3
expected: 5
high: 10
unit: "days"
This tells the simulator: in the best case, the task takes about 3 days; most likely it takes about 5 days; in a difficult scenario, it could take up to 10 days. Because unit: "days" is specified, the simulator converts these values to hours internally (using the project's hours_per_day setting, which defaults to 8). The simulator then samples from this range in every iteration, producing a distribution of task durations across the full simulation.
Choosing good range values¶
The three values are not arbitrary guesses. They carry specific meaning:
-
lowis not the theoretical fastest time if everything goes perfectly. It is the shortest duration that is still realistic given the scope of work. Ask: "If things go smoothly, how fast could this realistically be done?" -
expectedis the duration you would expect under normal conditions. It represents the mode — the single most probable outcome. Ask: "If I had to pick one number for this task, what would it be?" -
highis not a catastrophic worst case. It is the longest duration that is credibly possible if several things go wrong, but without extraordinary events like losing the entire team. Ask: "If this task hits significant headwinds, how long could it take?"
The spread between low and high reflects how uncertain you are. A narrow range (e.g., 4 / 5 / 6) means high confidence. A wide range (e.g., 3 / 5 / 15) means substantial uncertainty, and the simulation results will reflect that.
Asymmetric ranges¶
In practice, most software tasks have more upside risk than downside opportunity. It is common for the distance between expected and high to be larger than the distance between low and expected. This naturally produces a right-skewed distribution — reflecting the reality that tasks are more likely to run over than to finish early by the same margin.
Here, the best-case savings is 2 days (5 minus 3), but the worst-case overrun is 10 days (15 minus 5). This kind of asymmetry is realistic and the triangular distribution handles it naturally.
Near-deterministic estimates¶
Sometimes a task has very little uncertainty — for example, a well-understood routine task with a known duration. You might be tempted to set low, expected, and high to the same value.
However, the triangular distribution requires low < high. Setting all three values equal will produce a validation error at sampling time. To model a near-deterministic task, use a very narrow range:
This effectively produces a duration of approximately 5 days in every iteration, with negligible variation. The sampled values will be very close to 5.0 but not exactly identical, which is usually close enough for practical purposes.
Probability distributions¶
The estimate range defines the inputs. The probability distribution defines how values are sampled from that range. mcprojsim supports two distributions.
Triangular distribution (default)¶
The triangular distribution is the default and most commonly used distribution in project estimation. It is defined by three parameters — minimum, mode, and maximum — which correspond directly to the low, expected, and high fields in the estimate.
Properties:
| Property | Description |
|---|---|
| Shape | Triangle-shaped probability density |
| Parameters | low, expected (mode), high |
| Support | Values between low and high only |
| Skewness | Determined by position of expected within the range |
| Implementation | numpy.random.triangular |
When to use it:
- When the team can provide three-point estimates (optimistic, likely, pessimistic)
- When you want a bounded distribution — no sampled value can fall outside the stated range
- When you want an intuitive model that is easy to explain to stakeholders
- For most software estimation tasks — this is the recommended default
Characteristics:
The triangular distribution concentrates probability around the expected value and tapers linearly toward the extremes. It guarantees that no sample will be less than low or greater than high, which can be reassuring when the team has confidence in the boundaries.
If expected is centered between low and high, the distribution is symmetric. If expected is closer to low (common in software estimation), the distribution is right-skewed — producing a longer tail toward the high end.
Specification:
The triangular distribution is the default, so you do not need to specify it explicitly. Both of the following are equivalent:
# Implicit (triangular is the default)
estimate:
low: 3
expected: 5
high: 10
unit: "days"
# Explicit
estimate:
distribution: "triangular"
low: 3
expected: 5
high: 10
unit: "days"
Distribution precedence¶
The distribution used for a task is resolved in this order, from highest to lowest priority:
- Per-task
distributionfield — set directly on a task'sestimateblock. Always takes precedence. - Project-level
distributionfield — set underproject:in the project file. Acts as the default for all tasks in that project. - Built-in default —
triangularwhen nothing else is specified.
This means you can set distribution: lognormal once at the project level and get log-normal sampling for every task without touching each individual task, while still overriding specific tasks back to triangular (or another distribution) where needed.
There is currently no global --distribution CLI override for simulate.
Example — project-wide lognormal with one triangular override:
project:
name: "Research Project"
start_date: "2026-04-01"
distribution: "lognormal" # all tasks default to lognormal
tasks:
- id: "task_001"
name: "Write specification"
estimate: # inherits lognormal from project
low: 1
expected: 3
high: 8
unit: "days"
- id: "task_002"
name: "Set up CI pipeline"
estimate:
distribution: "triangular" # overrides project default for this task only
low: 0.5
expected: 1
high: 2
unit: "days"
Log-normal distribution¶
The log-normal distribution is an alternative that produces a right-skewed, unbounded distribution. It is useful for tasks where the upside risk (overrun) is potentially much larger than the downside opportunity (early finish).
mcprojsim implements this as a shifted log-normal so end users can keep
working with the same low, expected, and high fields they already use for
triangular estimates.
Properties:
| Property | Description |
|---|---|
| Shape | Right-skewed, long tail toward high values |
| Parameters | low, expected, high, plus configured percentile for high |
| Support | All values greater than low |
| Skewness | Always right-skewed; heavier tail with larger fitted sigma |
| Implementation | numpy.random.lognormal |
Internally the simulator defines a shifted variable:
$$Y = X - \text{low}$$
where $X$ is the actual duration and $Y$ follows a standard log-normal distribution.
The inputs are interpreted as:
low: hard minimum / shiftexpected: mode of $X$high: configured percentile of $X$ (P95 by default)
This gives:
$$e^{\mu - \sigma^2} = \text{expected} - \text{low}$$
and
$$e^{\mu + z_p\sigma} = \text{high} - \text{low}$$
where $z_p$ is the z-score for the configured percentile. For the default P95, $z_p \approx 1.645$.
Subtracting the two equations yields:
$$\sigma^2 + z_p\sigma = \ln(\text{high} - \text{low}) - \ln(\text{expected} - \text{low})$$
The simulator solves that quadratic for the positive $\sigma$, then computes:
$$\mu = \ln(\text{expected} - \text{low}) + \sigma^2$$
When to use it:
- For tasks with significant right-tail risk — where overruns could be much larger than expected
- When you are uncertain about the upper bound — the log-normal has no maximum, which may better represent truly open-ended tasks
- For research-oriented work, prototyping, or integration tasks with high unknowns
- When historical data suggests log-normal effort patterns (this is supported by research in some software estimation contexts)
When not to use it:
- When you have clear, defensible bounds on the task duration — in that case, a triangular distribution is more appropriate
- When stakeholders need guarantees that the sampled value will not exceed a certain threshold — the log-normal can produce extreme outliers
- When the team is not comfortable with unbounded estimates
Specification:
Here, 2 days is the minimum, 5 days is the most likely outcome, and 14 days is
interpreted as the configured high percentile (P95 by default). Wider gaps
between expected and high produce a heavier right tail.
Configuring the log-normal high percentile¶
The high value for log-normal estimates is interpreted using the configuration setting lognormal.high_percentile.
Allowed values are: 70, 75, 80, 85, 90, 95, 99.
- Lower values (for example
80) treathighas a less extreme percentile and produce a lighter right tail. - Higher values (for example
99) treathighas a more extreme percentile and produce a heavier right tail.
Example: a research task with high uncertainty
tasks:
- id: "prototype"
name: "Prototype ML model"
estimate:
distribution: "lognormal"
low: 4
expected: 10
high: 30
unit: "days"
dependencies: []
Here, the most likely duration is 10 days, but the long right tail means that in some iterations the sampled value could be 20 or 30 days — reflecting the genuine uncertainty in exploratory work.
Comparing the two distributions¶
| Aspect | Triangular | Log-normal |
|---|---|---|
| Bounded | Yes — samples always within [min, max] | No — no upper bound |
| Parameters | low, expected, high |
low, expected, high + configured high percentile |
| Skewness | Depends on parameter placement | Always right-skewed |
| Intuition | Easy to explain to non-technical stakeholders | Requires more statistical background |
| Extreme values | Impossible beyond stated bounds | Possible — long tail |
| Recommended for | Most estimation tasks | Tasks with open-ended risk |
For most projects, the triangular distribution is the right choice. It is intuitive, bounded, and maps naturally to how teams think about estimates. The log-normal distribution is a specialized tool for tasks where the unbounded right tail better reflects reality.
Why is log-normal a good model for software (or project) estimation?¶
Individual task durations are often observed to follow a log-normal distribution in empirical studies of projects and software projects in particular. This can be explained by noticing that task durations are influenced by many small, multiplicative factors — such as the complexity of the work, the efficiency of the team, the quality of requirements, and unforeseen issues that arise during execution. When you have a process that is influenced by many independent multiplicative factors, the resulting distribution of outcomes tends to be log-normal. This can be easily seen by observing that if an estimate can be written as
$$X = X_0 \times F_1 \times F_2 \times ... \times F_n$$
where $X_0$ is the base estimate and $F_i$ are the multiplicative factors, then taking the logarithm gives:
$$\ln(X) = \ln(X_0) + \ln(F_1) + \ln(F_2) + ... + \ln(F_n)$$
If we assume the $\ln(F_i)$ are independent and identically distributed, then by the Central Limit Theorem, $\ln(X)$ will tend to be normally distributed, which means that $X$ is log-normally distributed.
\newpage
T-shirt size estimates¶
T-shirt sizing is a relative estimation technique where tasks are classified into sizes such as XS, S, M, L, XL, and XXL, scoped by named categories (bug, story, epic, business, initiative). This is useful when teams need different calibration levels across planning horizons.
In mcprojsim, each T-shirt size is mapped to a numeric range (low, expected, high) inside a category in the configuration file. During simulation, a bare value like M resolves through t_shirt_size_default_category (default: epic), while a qualified value like epic.M resolves directly.
Default T-shirt size mappings¶
The default unit for T-shirt sizes is hours (configurable via t_shirt_size_unit in the configuration file).
The built-in default category is epic, so a bare value like M resolves as epic.M unless you change t_shirt_size_default_category or pass --tshirt-category on the CLI.
| Category | Size | low (hours) | expected (hours) | high (hours) |
|---|---|---|---|---|
bug |
XS |
0.5 | 1 | 4 |
bug |
S |
1 | 3 | 10 |
bug |
M |
3 | 8 | 24 |
bug |
L |
8 | 20 | 60 |
bug |
XL |
20 | 40 | 100 |
bug |
XXL |
40 | 80 | 200 |
story |
XS |
3 | 5 | 15 |
story |
S |
5 | 16 | 40 |
story |
M |
40 | 60 | 120 |
story |
L |
160 | 240 | 500 |
story |
XL |
320 | 400 | 750 |
story |
XXL |
400 | 500 | 1200 |
epic |
XS |
20 | 40 | 60 |
epic |
S |
60 | 120 | 170 |
epic |
M |
120 | 240 | 400 |
epic |
L |
290 | 480 | 700 |
epic |
XL |
600 | 1000 | 1500 |
epic |
XXL |
1200 | 2000 | 3200 |
business |
XS |
400 | 800 | 2000 |
business |
S |
800 | 2000 | 5000 |
business |
M |
2000 | 4000 | 10000 |
business |
L |
4000 | 8000 | 20000 |
business |
XL |
8000 | 16000 | 40000 |
business |
XXL |
16000 | 32000 | 80000 |
initiative |
XS |
2000 | 4000 | 10000 |
initiative |
S |
4000 | 10000 | 25000 |
initiative |
M |
10000 | 20000 | 50000 |
initiative |
L |
20000 | 40000 | 100000 |
initiative |
XL |
40000 | 80000 | 200000 |
initiative |
XXL |
80000 | 160000 | 400000 |
These category-specific defaults let you keep the same symbolic size scale while tuning absolute magnitude for different planning scopes.
Specifying a T-shirt size estimate¶
T-shirt size estimates must not include a unit field in the project file. The unit is determined by the configuration file's t_shirt_size_unit setting (default: "hours").
You can also use a qualified value:
Bare long-form aliases are accepted too, for example:
With the built-in defaults, the bare "M" example above is equivalent to writing:
If you want story-scale values instead, either use a qualified value (story.M) or set t_shirt_size_default_category: story in your configuration.
The resolution happens automatically when the simulation runs. The resolved values are then converted to hours internally (if they are not already in hours) using the project's hours_per_day setting.
Including unit on a T-shirt size estimate is a validation error:
# INVALID — will produce a validation error
estimate:
t_shirt_size: "M"
unit: "days" # ERROR: T-shirt size estimates must not specify 'unit'
Full example: project using T-shirt sizes¶
project:
name: "Tiny Landing Page"
description: "T-shirt sizing example"
start_date: "2026-03-01"
confidence_levels: [50, 80, 90]
hours_per_day: 8
tasks:
- id: "task_001"
name: "Design page"
estimate:
t_shirt_size: "S"
dependencies: []
uncertainty_factors:
team_experience: "high"
requirements_maturity: "high"
- id: "task_002"
name: "Build page"
estimate:
t_shirt_size: "M"
dependencies: ["task_001"]
uncertainty_factors:
team_experience: "medium"
technical_complexity: "medium"
- id: "task_003"
name: "Deploy page"
estimate:
t_shirt_size: "XS"
dependencies: ["task_002"]
Note that no unit field appears on any task — the unit is taken from the configuration.
\newpage
Customizing T-shirt sizes in the configuration file¶
The default mappings can be overridden in the configuration file. This allows organizations to calibrate the sizes to match their own team velocity and task granularity. For example, a team that works in shorter cycles might define smaller ranges:
# config.yaml
t_shirt_sizes:
story:
M:
low: 45
expected: 65
high: 130
epic:
M:
low: 240
expected: 520
high: 1400
t_shirt_size_default_category: epic
Any category/size values you define in the configuration file override those defaults while untouched categories and sizes remain available.
Choosing the unit for T-shirt sizes¶
The numeric ranges in the T-shirt size mappings are interpreted in the unit specified by t_shirt_size_unit in the configuration file. The default is "hours":
# config.yaml — T-shirt sizes in hours (the default)
t_shirt_size_unit: "hours"
t_shirt_sizes:
story:
S:
low: 1
expected: 2
high: 4 # 1-4 hours
M:
low: 3
expected: 5
high: 8 # 3-8 hours
L:
low: 5
expected: 8
high: 13 # 5-13 hours
If your team thinks about T-shirt sizes in terms of working days rather than hours, set t_shirt_size_unit to "days". The simulator will then convert the ranges to hours using hours_per_day:
# config.yaml — T-shirt sizes in days
t_shirt_size_unit: "days"
t_shirt_sizes:
story:
S:
low: 0.5
expected: 1
high: 2 # 0.5-2 days -> 4-16 hours (at 8 hours/day)
M:
low: 1
expected: 2
high: 4 # 1-4 days -> 8-32 hours
L:
low: 2
expected: 4
high: 7 # 2-7 days -> 16-56 hours
The unit setting applies to all T-shirt sizes in the configuration. You cannot mix units across individual sizes — the t_shirt_size_unit value governs the entire mapping. The project file never specifies a unit for T-shirt size estimates; the unit is always determined by this configuration setting.
Story point estimates¶
Story points are a common estimation unit in agile teams. In mcprojsim, story point values are mapped to day-based numeric ranges in the configuration file, similar to T-shirt sizes.
Default story point mappings¶
The default unit for story points is days (configurable via story_point_unit in the configuration file).
| Story points | low (days) | expected (days) | high (days) |
|---|---|---|---|
| 1 | 0.5 | 1 | 3 |
| 2 | 1 | 2 | 4 |
| 3 | 1.5 | 3 | 5 |
| 5 | 3 | 5 | 8 |
| 8 | 5 | 8 | 15 |
| 13 | 8 | 13 | 21 |
| 21 | 13 | 21 | 34 |
The allowed values are: 1, 2, 3, 5, 8, 13, 21. Other values are rejected during validation.
Specifying a story point estimate¶
Story point estimates must not include a unit field in the project file. The unit is determined by the configuration file's story_point_unit setting (default: "days").
Including unit on a story point estimate is a validation error:
# INVALID — will produce a validation error
estimate:
story_points: 5
unit: "days" # ERROR: Story Point estimates must not specify 'unit'
Full example: project using story points¶
project:
name: "Tiny Landing Page"
description: "Story point estimation example"
start_date: "2026-03-01"
confidence_levels: [50, 80, 90]
hours_per_day: 8
tasks:
- id: "task_001"
name: "Design page"
estimate:
story_points: 2
dependencies: []
uncertainty_factors:
team_experience: "high"
requirements_maturity: "high"
- id: "task_002"
name: "Build page"
estimate:
story_points: 5
dependencies: ["task_001"]
uncertainty_factors:
team_experience: "medium"
technical_complexity: "medium"
Note that no unit field appears on any task — the unit is taken from the configuration (story_point_unit, which defaults to "days").
Customizing story point mappings in the configuration file¶
Different teams have different velocity patterns. The configuration file lets you adjust the day-based ranges that each story point value maps to:
# config.yaml
story_points:
1:
low: 0.5
expected: 1
high: 2.5
2:
low: 1
expected: 2
high: 3.5
5:
low: 3.5
expected: 5.5
high: 9
You only need to include the story point values you want to override. Any values not specified in your configuration will use the built-in defaults. Note that you can only use values from the allowed set (1, 2, 3, 5, 8, 13, 21) — the allowed values are defined in the code, not in configuration.
\newpage
Choosing the unit for story points¶
The numeric ranges in the story point mappings are interpreted in the unit specified by story_point_unit in the configuration file. The default is "days":
# config.yaml — story points in days (the default)
story_point_unit: "days"
story_points:
1:
low: 0.5
expected: 1
high: 3 # 0.5–3 days → 4–24 hours (at 8 hours/day)
5:
low: 3
expected: 5
high: 8 # 3–8 days → 24–64 hours
If your team calibrates story points directly in hours, set story_point_unit to "hours":
# config.yaml — story points in hours
story_point_unit: "hours"
story_points:
1:
low: 1
expected: 3
high: 6 # 1–6 hours
5:
low: 8
expected: 16
high: 32 # 8–32 hours
As with T-shirt sizes, the unit setting applies to all story point mappings in the configuration. The project file never specifies a unit for story point estimates — the unit is always determined by story_point_unit.
Note: The
t_shirt_size_unitandstory_point_unitsettings are independent. It is perfectly valid to have T-shirt sizes in hours and story points in days (the defaults), or any other combination.
Mixing estimation methods¶
A single project can use different estimation methods for different tasks. This is useful when some tasks are well-understood enough for explicit day estimates while others are better expressed as relative sizes.
tasks:
- id: "research"
name: "Technology research"
estimate:
distribution: "lognormal"
low: 3
expected: 8
high: 20
unit: "days"
dependencies: []
- id: "design"
name: "Architecture design"
estimate:
t_shirt_size: "L"
dependencies: ["research"]
- id: "implementation"
name: "Core implementation"
estimate:
low: 10
expected: 15
high: 25
unit: "days"
dependencies: ["design"]
- id: "testing"
name: "Integration testing"
estimate:
story_points: 8
dependencies: ["implementation"]
All four estimation methods are combined in one project. Each task's estimate is resolved and sampled independently using the same simulation pipeline. The simulator converts all values to hours internally using the appropriate unit for each estimate method.
Implementation detail: if a symbolic estimate (t_shirt_size or story_points) is present together with explicit numeric fields (low / expected / high), the symbolic estimate path is used and numeric fields are effectively ignored.
Recommended authoring style: avoid mixing symbolic and explicit fields on the same task. Use exactly one method per task to keep intent unambiguous.
The unit field¶
The unit field specifies the time unit for numeric estimate values. The simulator uses this field to convert all values to hours internally, which is the canonical unit used throughout the simulation.
Supported values¶
The unit field accepts exactly three values:
| Value | Meaning | Conversion to hours |
|---|---|---|
"hours" |
Working hours | Used as-is (1 hour = 1 hour) |
"days" |
Working days | Multiplied by hours_per_day (default 8) |
"weeks" |
Working weeks | Multiplied by hours_per_day × 5 (default 40) |
Any other value is a validation error.
Defaults by estimate type¶
| Estimate type | Default unit | unit field allowed? |
|---|---|---|
| Explicit range | "hours" |
Yes — "hours", "days", or "weeks" |
| T-shirt size | (from config) | No — specifying unit is a validation error |
| Story points | (from config) | No — specifying unit is a validation error |
For explicit range estimates, the default unit is "hours". If you omit the unit field, your numeric values are interpreted as hours.
For T-shirt sizes and story points, the unit is controlled by the configuration file (t_shirt_size_unit and story_point_unit respectively). The project file must not include a unit field for these estimate types.
The hours_per_day setting¶
The project metadata supports an hours_per_day field (default: 8.0) that controls how days and weeks are converted to hours:
This setting affects:
- conversion of
unit: "days"values (multiplied byhours_per_day) - conversion of
unit: "weeks"values (multiplied byhours_per_day × 5) - conversion of simulation results from hours back to working days for reporting
Unit conversion is automatic¶
The simulator automatically converts all estimate values to hours before simulation begins. This means you can safely mix units across tasks in the same project:
tasks:
- id: "quick_fix"
estimate:
low: 2
expected: 4
high: 8
unit: "hours" # Small task estimated in hours
- id: "major_feature"
estimate:
low: 2
expected: 4
high: 8
unit: "days" # Large task estimated in days
The simulator converts the second task's values to hours (2×8=16, 4×8=32, 8×8=64) before sampling. The two tasks are compared on a common scale.
Simulation output¶
All simulation results are reported in hours. The CLI and export formats also show working days (computed as ceil(hours / hours_per_day)) and projected delivery dates (skipping weekends, based on start_date).
Unit field for T-shirt sizes and story points¶
When a T-shirt size or story point estimate is resolved during simulation, the numeric values come from the configuration file. The unit for those values is also defined in the configuration:
t_shirt_size_unit: defaults to"hours"story_point_unit: defaults to"days"
The resolved values are then converted to hours using the same conversion logic. This means a story point estimate of 5 with default configuration resolves to min=3, expected=5, max=8 in days, which the simulator converts to min=24, expected=40, max=64 in hours.
Validation rules¶
mcprojsim validates every task estimate before the simulation runs. Understanding the validation rules helps avoid errors:
| Rule | Applies to | Error if violated |
|---|---|---|
low ≤ expected ≤ high |
Triangular distribution | Yes — values must be in order |
low < high |
Triangular distribution | Yes — NumPy requires strict inequality |
expected > 0 |
All explicit estimates | Yes — zero or negative not allowed |
low ≥ 0 |
Triangular distribution | Yes — negative values not allowed |
low < expected < high |
Log-normal distribution | Yes — shifted fit requires a strict range |
low, expected, high all provided |
Log-normal distribution | Yes — all three required |
low, expected, high all provided |
Triangular distribution | Yes — all three required |
| Only one symbolic type | T-shirt / story point | Yes — cannot use both on one task |
At least one estimate mode provided (expected or symbolic) |
All tasks | Yes — estimate cannot be empty |
| Story point value in allowed set | Story points | Yes — must be 1, 2, 3, 5, 8, 13, or 21 |
unit must be "hours", "days", or "weeks" |
Explicit estimates | Yes — free-form strings not accepted |
No unit on symbolic estimates |
T-shirt / story point | Yes — unit comes from config |
t_shirt_size token shape must be <size> or <category>.<size> |
T-shirt size | Yes — invalid token formats fail validation |
t_shirt_size category and size must exist in active config |
T-shirt size | Yes — unknown category/size fails resolution |
Summary¶
| Estimation method | Required fields | Distribution | Good for |
|---|---|---|---|
| Explicit range (triangular) | low, expected, high |
Triangular (bounded) | Well-understood tasks with clear bounds |
| Explicit range (log-normal) | low, expected, high, distribution: "lognormal" |
Shifted log-normal | Exploratory tasks with open-ended risk |
| T-shirt size | t_shirt_size |
Inherits project/task distribution after config lookup | Relative estimation, early planning |
| Story points | story_points |
Inherits project/task distribution after config lookup | Agile teams using story point practices |
All methods produce the same kind of output: a sampled duration for each iteration. The choice of method depends on what information the team is comfortable providing, not on any difference in simulation behavior.