Task Estimation

This chapter explains how individual tasks are estimated in mcprojsim and how those estimates drive the Monte Carlo simulation. Every task in a project file needs an effort estimate. That estimate is not a single fixed number — it is a structured description of plausible effort that the simulator samples from in each iteration.

The goal of this chapter is to explain all supported estimation methods, the probability distributions behind them, and how to specify each one in a project file.

How estimation works in the simulation

In each Monte Carlo iteration, the simulator processes every task as follows:

  1. Read the estimate from the task definition.
  2. Resolve symbolic estimates (T-shirt sizes or story points) into numeric ranges using the configuration file.
  3. Sample a base duration from the specified probability distribution.
  4. Apply uncertainty factors (multiplicative adjustment).
  5. Evaluate task-level risks (additive impact if triggered).

The result is the task's effective duration for that iteration. Over thousands of iterations, the sampled values form a distribution that captures the inherent uncertainty in the estimate.

This chapter focuses on steps 1 through 3. Uncertainty factors and risks are covered in Uncertainty Factors and Risks.

Estimation methods at a glance

mcprojsim supports four ways to express task effort. Each method provides the same information to the simulator — a probability distribution to sample from — but is suited to different estimation contexts.

Method Input Resolved to Best for
Explicit range (triangular) low, expected, high Used directly Teams comfortable giving numeric estimates with bounded outcomes
Explicit range (log-normal) low, expected, high, distribution: "lognormal" Used directly Tasks with significant right-tail risk or open-ended uncertainty
T-shirt size t_shirt_size (e.g., "M" or "epic.M") Looked up in config → low, expected, high Early-stage or relative estimation
Story points story_points (e.g., 5) Looked up in config → low, expected, high Teams using story point estimation practices

All four methods ultimately feed into the same simulation machinery. T-shirt sizes and story points are convenience mappings that resolve to explicit ranges before sampling begins.

Accepted field aliases

For explicit ranges, the estimate model accepts these equivalent field names:

Canonical field Accepted alias
low min
expected most_likely
high max

You can use either form in YAML or TOML. They are interpreted identically.

Explicit range estimates

The most direct way to estimate a task is to provide three values that describe the range of plausible effort:

Parameter Meaning Required
low The shortest plausible duration (optimistic) Yes
expected The expected duration under normal conditions Yes
high The longest plausible duration (pessimistic) Yes
unit The time unit: "hours", "days", or "weeks" (default: "hours") No

The three values must satisfy: lowexpectedhigh.

Basic example

tasks:
  - id: "task_001"
    name: "Database schema design"
    estimate:
      low: 3
      expected: 5
      high: 10
      unit: "days"

This tells the simulator: in the best case, the task takes about 3 days; most likely it takes about 5 days; in a difficult scenario, it could take up to 10 days. Because unit: "days" is specified, the simulator converts these values to hours internally (using the project's hours_per_day setting, which defaults to 8). The simulator then samples from this range in every iteration, producing a distribution of task durations across the full simulation.

Choosing good range values

The three values are not arbitrary guesses. They carry specific meaning:

  • low is not the theoretical fastest time if everything goes perfectly. It is the shortest duration that is still realistic given the scope of work. Ask: "If things go smoothly, how fast could this realistically be done?"

  • expected is the duration you would expect under normal conditions. It represents the mode — the single most probable outcome. Ask: "If I had to pick one number for this task, what would it be?"

  • high is not a catastrophic worst case. It is the longest duration that is credibly possible if several things go wrong, but without extraordinary events like losing the entire team. Ask: "If this task hits significant headwinds, how long could it take?"

The spread between low and high reflects how uncertain you are. A narrow range (e.g., 4 / 5 / 6) means high confidence. A wide range (e.g., 3 / 5 / 15) means substantial uncertainty, and the simulation results will reflect that.

Asymmetric ranges

In practice, most software tasks have more upside risk than downside opportunity. It is common for the distance between expected and high to be larger than the distance between low and expected. This naturally produces a right-skewed distribution — reflecting the reality that tasks are more likely to run over than to finish early by the same margin.

estimate:
  low: 3
  expected: 5
  high: 15
  unit: "days"

Here, the best-case savings is 2 days (5 minus 3), but the worst-case overrun is 10 days (15 minus 5). This kind of asymmetry is realistic and the triangular distribution handles it naturally.

Near-deterministic estimates

Sometimes a task has very little uncertainty — for example, a well-understood routine task with a known duration. You might be tempted to set low, expected, and high to the same value.

However, the triangular distribution requires low < high. Setting all three values equal will produce a validation error at sampling time. To model a near-deterministic task, use a very narrow range:

estimate:
  low: 4.9
  expected: 5
  high: 5.1
  unit: "days"

This effectively produces a duration of approximately 5 days in every iteration, with negligible variation. The sampled values will be very close to 5.0 but not exactly identical, which is usually close enough for practical purposes.

Probability distributions

The estimate range defines the inputs. The probability distribution defines how values are sampled from that range. mcprojsim supports two distributions.

Triangular distribution (default)

The triangular distribution is the default and most commonly used distribution in project estimation. It is defined by three parameters — minimum, mode, and maximum — which correspond directly to the low, expected, and high fields in the estimate.

Properties:

Property Description
Shape Triangle-shaped probability density
Parameters low, expected (mode), high
Support Values between low and high only
Skewness Determined by position of expected within the range
Implementation numpy.random.triangular

When to use it:

  • When the team can provide three-point estimates (optimistic, likely, pessimistic)
  • When you want a bounded distribution — no sampled value can fall outside the stated range
  • When you want an intuitive model that is easy to explain to stakeholders
  • For most software estimation tasks — this is the recommended default

Characteristics:

The triangular distribution concentrates probability around the expected value and tapers linearly toward the extremes. It guarantees that no sample will be less than low or greater than high, which can be reassuring when the team has confidence in the boundaries.

If expected is centered between low and high, the distribution is symmetric. If expected is closer to low (common in software estimation), the distribution is right-skewed — producing a longer tail toward the high end.

Specification:

The triangular distribution is the default, so you do not need to specify it explicitly. Both of the following are equivalent:

# Implicit (triangular is the default)
estimate:
  low: 3
  expected: 5
  high: 10
  unit: "days"

# Explicit
estimate:
  distribution: "triangular"
  low: 3
  expected: 5
  high: 10
  unit: "days"

Distribution precedence

The distribution used for a task is resolved in this order, from highest to lowest priority:

  1. Per-task distribution field — set directly on a task's estimate block. Always takes precedence.
  2. Project-level distribution field — set under project: in the project file. Acts as the default for all tasks in that project.
  3. Built-in defaulttriangular when nothing else is specified.

This means you can set distribution: lognormal once at the project level and get log-normal sampling for every task without touching each individual task, while still overriding specific tasks back to triangular (or another distribution) where needed.

There is currently no global --distribution CLI override for simulate.

Example — project-wide lognormal with one triangular override:

project:
  name: "Research Project"
  start_date: "2026-04-01"
  distribution: "lognormal"          # all tasks default to lognormal

tasks:
  - id: "task_001"
    name: "Write specification"
    estimate:                         # inherits lognormal from project
      low: 1
      expected: 3
      high: 8
      unit: "days"

  - id: "task_002"
    name: "Set up CI pipeline"
    estimate:
      distribution: "triangular"     # overrides project default for this task only
      low: 0.5
      expected: 1
      high: 2
      unit: "days"

Log-normal distribution

The log-normal distribution is an alternative that produces a right-skewed, unbounded distribution. It is useful for tasks where the upside risk (overrun) is potentially much larger than the downside opportunity (early finish).

mcprojsim implements this as a shifted log-normal so end users can keep working with the same low, expected, and high fields they already use for triangular estimates.

Properties:

Property Description
Shape Right-skewed, long tail toward high values
Parameters low, expected, high, plus configured percentile for high
Support All values greater than low
Skewness Always right-skewed; heavier tail with larger fitted sigma
Implementation numpy.random.lognormal

Internally the simulator defines a shifted variable:

$$Y = X - \text{low}$$

where $X$ is the actual duration and $Y$ follows a standard log-normal distribution.

The inputs are interpreted as:

  • low: hard minimum / shift
  • expected: mode of $X$
  • high: configured percentile of $X$ (P95 by default)

This gives:

$$e^{\mu - \sigma^2} = \text{expected} - \text{low}$$

and

$$e^{\mu + z_p\sigma} = \text{high} - \text{low}$$

where $z_p$ is the z-score for the configured percentile. For the default P95, $z_p \approx 1.645$.

Subtracting the two equations yields:

$$\sigma^2 + z_p\sigma = \ln(\text{high} - \text{low}) - \ln(\text{expected} - \text{low})$$

The simulator solves that quadratic for the positive $\sigma$, then computes:

$$\mu = \ln(\text{expected} - \text{low}) + \sigma^2$$

When to use it:

  • For tasks with significant right-tail risk — where overruns could be much larger than expected
  • When you are uncertain about the upper bound — the log-normal has no maximum, which may better represent truly open-ended tasks
  • For research-oriented work, prototyping, or integration tasks with high unknowns
  • When historical data suggests log-normal effort patterns (this is supported by research in some software estimation contexts)

When not to use it:

  • When you have clear, defensible bounds on the task duration — in that case, a triangular distribution is more appropriate
  • When stakeholders need guarantees that the sampled value will not exceed a certain threshold — the log-normal can produce extreme outliers
  • When the team is not comfortable with unbounded estimates

Specification:

estimate:
  distribution: "lognormal"
  low: 2
  expected: 5
  high: 14
  unit: "days"

Here, 2 days is the minimum, 5 days is the most likely outcome, and 14 days is interpreted as the configured high percentile (P95 by default). Wider gaps between expected and high produce a heavier right tail.

Configuring the log-normal high percentile

The high value for log-normal estimates is interpreted using the configuration setting lognormal.high_percentile.

lognormal:
  high_percentile: 95

Allowed values are: 70, 75, 80, 85, 90, 95, 99.

  • Lower values (for example 80) treat high as a less extreme percentile and produce a lighter right tail.
  • Higher values (for example 99) treat high as a more extreme percentile and produce a heavier right tail.

Example: a research task with high uncertainty

tasks:
  - id: "prototype"
    name: "Prototype ML model"
    estimate:
      distribution: "lognormal"
      low: 4
      expected: 10
      high: 30
      unit: "days"
    dependencies: []

Here, the most likely duration is 10 days, but the long right tail means that in some iterations the sampled value could be 20 or 30 days — reflecting the genuine uncertainty in exploratory work.

Comparing the two distributions

Aspect Triangular Log-normal
Bounded Yes — samples always within [min, max] No — no upper bound
Parameters low, expected, high low, expected, high + configured high percentile
Skewness Depends on parameter placement Always right-skewed
Intuition Easy to explain to non-technical stakeholders Requires more statistical background
Extreme values Impossible beyond stated bounds Possible — long tail
Recommended for Most estimation tasks Tasks with open-ended risk

For most projects, the triangular distribution is the right choice. It is intuitive, bounded, and maps naturally to how teams think about estimates. The log-normal distribution is a specialized tool for tasks where the unbounded right tail better reflects reality.

Why is log-normal a good model for software (or project) estimation?

Individual task durations are often observed to follow a log-normal distribution in empirical studies of projects and software projects in particular. This can be explained by noticing that task durations are influenced by many small, multiplicative factors — such as the complexity of the work, the efficiency of the team, the quality of requirements, and unforeseen issues that arise during execution. When you have a process that is influenced by many independent multiplicative factors, the resulting distribution of outcomes tends to be log-normal. This can be easily seen by observing that if an estimate can be written as

$$X = X_0 \times F_1 \times F_2 \times ... \times F_n$$

where $X_0$ is the base estimate and $F_i$ are the multiplicative factors, then taking the logarithm gives:

$$\ln(X) = \ln(X_0) + \ln(F_1) + \ln(F_2) + ... + \ln(F_n)$$

If we assume the $\ln(F_i)$ are independent and identically distributed, then by the Central Limit Theorem, $\ln(X)$ will tend to be normally distributed, which means that $X$ is log-normally distributed.

\newpage

T-shirt size estimates

T-shirt sizing is a relative estimation technique where tasks are classified into sizes such as XS, S, M, L, XL, and XXL, scoped by named categories (bug, story, epic, business, initiative). This is useful when teams need different calibration levels across planning horizons.

In mcprojsim, each T-shirt size is mapped to a numeric range (low, expected, high) inside a category in the configuration file. During simulation, a bare value like M resolves through t_shirt_size_default_category (default: epic), while a qualified value like epic.M resolves directly.

Default T-shirt size mappings

The default unit for T-shirt sizes is hours (configurable via t_shirt_size_unit in the configuration file).

The built-in default category is epic, so a bare value like M resolves as epic.M unless you change t_shirt_size_default_category or pass --tshirt-category on the CLI.

Category Size low (hours) expected (hours) high (hours)
bug XS 0.5 1 4
bug S 1 3 10
bug M 3 8 24
bug L 8 20 60
bug XL 20 40 100
bug XXL 40 80 200
story XS 3 5 15
story S 5 16 40
story M 40 60 120
story L 160 240 500
story XL 320 400 750
story XXL 400 500 1200
epic XS 20 40 60
epic S 60 120 170
epic M 120 240 400
epic L 290 480 700
epic XL 600 1000 1500
epic XXL 1200 2000 3200
business XS 400 800 2000
business S 800 2000 5000
business M 2000 4000 10000
business L 4000 8000 20000
business XL 8000 16000 40000
business XXL 16000 32000 80000
initiative XS 2000 4000 10000
initiative S 4000 10000 25000
initiative M 10000 20000 50000
initiative L 20000 40000 100000
initiative XL 40000 80000 200000
initiative XXL 80000 160000 400000

These category-specific defaults let you keep the same symbolic size scale while tuning absolute magnitude for different planning scopes.

Specifying a T-shirt size estimate

T-shirt size estimates must not include a unit field in the project file. The unit is determined by the configuration file's t_shirt_size_unit setting (default: "hours").

tasks:
  - id: "design_ui"
    name: "UI/UX Design"
    estimate:
      t_shirt_size: "M"
    dependencies: []

You can also use a qualified value:

estimate:
  t_shirt_size: "epic.M"

Bare long-form aliases are accepted too, for example:

estimate:
  t_shirt_size: "Medium"

With the built-in defaults, the bare "M" example above is equivalent to writing:

estimate:
  low: 120
  expected: 240
  high: 400
  unit: "hours"

If you want story-scale values instead, either use a qualified value (story.M) or set t_shirt_size_default_category: story in your configuration.

The resolution happens automatically when the simulation runs. The resolved values are then converted to hours internally (if they are not already in hours) using the project's hours_per_day setting.

Including unit on a T-shirt size estimate is a validation error:

# INVALID — will produce a validation error
estimate:
  t_shirt_size: "M"
  unit: "days"   # ERROR: T-shirt size estimates must not specify 'unit'

Full example: project using T-shirt sizes

project:
  name: "Tiny Landing Page"
  description: "T-shirt sizing example"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]
  hours_per_day: 8

tasks:
  - id: "task_001"
    name: "Design page"
    estimate:
      t_shirt_size: "S"
    dependencies: []
    uncertainty_factors:
      team_experience: "high"
      requirements_maturity: "high"

  - id: "task_002"
    name: "Build page"
    estimate:
      t_shirt_size: "M"
    dependencies: ["task_001"]
    uncertainty_factors:
      team_experience: "medium"
      technical_complexity: "medium"

  - id: "task_003"
    name: "Deploy page"
    estimate:
      t_shirt_size: "XS"
    dependencies: ["task_002"]

Note that no unit field appears on any task — the unit is taken from the configuration.

\newpage

Customizing T-shirt sizes in the configuration file

The default mappings can be overridden in the configuration file. This allows organizations to calibrate the sizes to match their own team velocity and task granularity. For example, a team that works in shorter cycles might define smaller ranges:

# config.yaml
t_shirt_sizes:
  story:
    M:
      low: 45
      expected: 65
      high: 130
  epic:
    M:
      low: 240
      expected: 520
      high: 1400

t_shirt_size_default_category: epic

Any category/size values you define in the configuration file override those defaults while untouched categories and sizes remain available.

Choosing the unit for T-shirt sizes

The numeric ranges in the T-shirt size mappings are interpreted in the unit specified by t_shirt_size_unit in the configuration file. The default is "hours":

# config.yaml — T-shirt sizes in hours (the default)
t_shirt_size_unit: "hours"

t_shirt_sizes:
  story:
    S:
      low: 1
      expected: 2
      high: 4       # 1-4 hours
    M:
      low: 3
      expected: 5
      high: 8       # 3-8 hours
    L:
      low: 5
      expected: 8
      high: 13      # 5-13 hours

If your team thinks about T-shirt sizes in terms of working days rather than hours, set t_shirt_size_unit to "days". The simulator will then convert the ranges to hours using hours_per_day:

# config.yaml — T-shirt sizes in days
t_shirt_size_unit: "days"

t_shirt_sizes:
  story:
    S:
      low: 0.5
      expected: 1
      high: 2       # 0.5-2 days -> 4-16 hours (at 8 hours/day)
    M:
      low: 1
      expected: 2
      high: 4       # 1-4 days -> 8-32 hours
    L:
      low: 2
      expected: 4
      high: 7       # 2-7 days -> 16-56 hours

The unit setting applies to all T-shirt sizes in the configuration. You cannot mix units across individual sizes — the t_shirt_size_unit value governs the entire mapping. The project file never specifies a unit for T-shirt size estimates; the unit is always determined by this configuration setting.

Story point estimates

Story points are a common estimation unit in agile teams. In mcprojsim, story point values are mapped to day-based numeric ranges in the configuration file, similar to T-shirt sizes.

Default story point mappings

The default unit for story points is days (configurable via story_point_unit in the configuration file).

Story points low (days) expected (days) high (days)
1 0.5 1 3
2 1 2 4
3 1.5 3 5
5 3 5 8
8 5 8 15
13 8 13 21
21 13 21 34

The allowed values are: 1, 2, 3, 5, 8, 13, 21. Other values are rejected during validation.

Specifying a story point estimate

Story point estimates must not include a unit field in the project file. The unit is determined by the configuration file's story_point_unit setting (default: "days").

tasks:
  - id: "task_001"
    name: "Design page"
    estimate:
      story_points: 5
    dependencies: []

Including unit on a story point estimate is a validation error:

# INVALID — will produce a validation error
estimate:
  story_points: 5
  unit: "days"   # ERROR: Story Point estimates must not specify 'unit'

Full example: project using story points

project:
  name: "Tiny Landing Page"
  description: "Story point estimation example"
  start_date: "2026-03-01"
  confidence_levels: [50, 80, 90]
  hours_per_day: 8

tasks:
  - id: "task_001"
    name: "Design page"
    estimate:
      story_points: 2
    dependencies: []
    uncertainty_factors:
      team_experience: "high"
      requirements_maturity: "high"
  - id: "task_002"
    name: "Build page"
    estimate:
      story_points: 5
    dependencies: ["task_001"]
    uncertainty_factors:
      team_experience: "medium"
      technical_complexity: "medium"
  - id: "task_003"
    name: "Deploy page"
    estimate:
      story_points: 1
    dependencies: ["task_002"]

Note that no unit field appears on any task — the unit is taken from the configuration (story_point_unit, which defaults to "days").

Customizing story point mappings in the configuration file

Different teams have different velocity patterns. The configuration file lets you adjust the day-based ranges that each story point value maps to:

# config.yaml
story_points:
  1:
    low: 0.5
    expected: 1
    high: 2.5
  2:
    low: 1
    expected: 2
    high: 3.5
  5:
    low: 3.5
    expected: 5.5
    high: 9

You only need to include the story point values you want to override. Any values not specified in your configuration will use the built-in defaults. Note that you can only use values from the allowed set (1, 2, 3, 5, 8, 13, 21) — the allowed values are defined in the code, not in configuration.

\newpage

Choosing the unit for story points

The numeric ranges in the story point mappings are interpreted in the unit specified by story_point_unit in the configuration file. The default is "days":

# config.yaml — story points in days (the default)
story_point_unit: "days"

story_points:
  1:
    low: 0.5
    expected: 1
    high: 3       # 0.5–3 days → 4–24 hours (at 8 hours/day)
  5:
    low: 3
    expected: 5
    high: 8       # 3–8 days → 24–64 hours

If your team calibrates story points directly in hours, set story_point_unit to "hours":

# config.yaml — story points in hours
story_point_unit: "hours"

story_points:
  1:
    low: 1
    expected: 3
    high: 6       # 1–6 hours
  5:
    low: 8
    expected: 16
    high: 32      # 8–32 hours

As with T-shirt sizes, the unit setting applies to all story point mappings in the configuration. The project file never specifies a unit for story point estimates — the unit is always determined by story_point_unit.

Note: The t_shirt_size_unit and story_point_unit settings are independent. It is perfectly valid to have T-shirt sizes in hours and story points in days (the defaults), or any other combination.

Mixing estimation methods

A single project can use different estimation methods for different tasks. This is useful when some tasks are well-understood enough for explicit day estimates while others are better expressed as relative sizes.

tasks:
  - id: "research"
    name: "Technology research"
    estimate:
      distribution: "lognormal"
      low: 3
      expected: 8
      high: 20
      unit: "days"
    dependencies: []

  - id: "design"
    name: "Architecture design"
    estimate:
      t_shirt_size: "L"
    dependencies: ["research"]

  - id: "implementation"
    name: "Core implementation"
    estimate:
      low: 10
      expected: 15
      high: 25
      unit: "days"
    dependencies: ["design"]

  - id: "testing"
    name: "Integration testing"
    estimate:
      story_points: 8
    dependencies: ["implementation"]

All four estimation methods are combined in one project. Each task's estimate is resolved and sampled independently using the same simulation pipeline. The simulator converts all values to hours internally using the appropriate unit for each estimate method.

Implementation detail: if a symbolic estimate (t_shirt_size or story_points) is present together with explicit numeric fields (low / expected / high), the symbolic estimate path is used and numeric fields are effectively ignored.

Recommended authoring style: avoid mixing symbolic and explicit fields on the same task. Use exactly one method per task to keep intent unambiguous.

The unit field

The unit field specifies the time unit for numeric estimate values. The simulator uses this field to convert all values to hours internally, which is the canonical unit used throughout the simulation.

Supported values

The unit field accepts exactly three values:

Value Meaning Conversion to hours
"hours" Working hours Used as-is (1 hour = 1 hour)
"days" Working days Multiplied by hours_per_day (default 8)
"weeks" Working weeks Multiplied by hours_per_day × 5 (default 40)

Any other value is a validation error.

Defaults by estimate type

Estimate type Default unit unit field allowed?
Explicit range "hours" Yes — "hours", "days", or "weeks"
T-shirt size (from config) No — specifying unit is a validation error
Story points (from config) No — specifying unit is a validation error

For explicit range estimates, the default unit is "hours". If you omit the unit field, your numeric values are interpreted as hours.

For T-shirt sizes and story points, the unit is controlled by the configuration file (t_shirt_size_unit and story_point_unit respectively). The project file must not include a unit field for these estimate types.

The hours_per_day setting

The project metadata supports an hours_per_day field (default: 8.0) that controls how days and weeks are converted to hours:

project:
  name: "My Project"
  start_date: "2026-03-01"
  hours_per_day: 6    # 6-hour productive work days

This setting affects:

  • conversion of unit: "days" values (multiplied by hours_per_day)
  • conversion of unit: "weeks" values (multiplied by hours_per_day × 5)
  • conversion of simulation results from hours back to working days for reporting

Unit conversion is automatic

The simulator automatically converts all estimate values to hours before simulation begins. This means you can safely mix units across tasks in the same project:

tasks:
  - id: "quick_fix"
    estimate:
      low: 2
      expected: 4
      high: 8
      unit: "hours"    # Small task estimated in hours

  - id: "major_feature"
    estimate:
      low: 2
      expected: 4
      high: 8
      unit: "days"     # Large task estimated in days

The simulator converts the second task's values to hours (2×8=16, 4×8=32, 8×8=64) before sampling. The two tasks are compared on a common scale.

Simulation output

All simulation results are reported in hours. The CLI and export formats also show working days (computed as ceil(hours / hours_per_day)) and projected delivery dates (skipping weekends, based on start_date).

Unit field for T-shirt sizes and story points

When a T-shirt size or story point estimate is resolved during simulation, the numeric values come from the configuration file. The unit for those values is also defined in the configuration:

  • t_shirt_size_unit: defaults to "hours"
  • story_point_unit: defaults to "days"

The resolved values are then converted to hours using the same conversion logic. This means a story point estimate of 5 with default configuration resolves to min=3, expected=5, max=8 in days, which the simulator converts to min=24, expected=40, max=64 in hours.

Validation rules

mcprojsim validates every task estimate before the simulation runs. Understanding the validation rules helps avoid errors:

Rule Applies to Error if violated
lowexpectedhigh Triangular distribution Yes — values must be in order
low < high Triangular distribution Yes — NumPy requires strict inequality
expected > 0 All explicit estimates Yes — zero or negative not allowed
low ≥ 0 Triangular distribution Yes — negative values not allowed
low < expected < high Log-normal distribution Yes — shifted fit requires a strict range
low, expected, high all provided Log-normal distribution Yes — all three required
low, expected, high all provided Triangular distribution Yes — all three required
Only one symbolic type T-shirt / story point Yes — cannot use both on one task
At least one estimate mode provided (expected or symbolic) All tasks Yes — estimate cannot be empty
Story point value in allowed set Story points Yes — must be 1, 2, 3, 5, 8, 13, or 21
unit must be "hours", "days", or "weeks" Explicit estimates Yes — free-form strings not accepted
No unit on symbolic estimates T-shirt / story point Yes — unit comes from config
t_shirt_size token shape must be <size> or <category>.<size> T-shirt size Yes — invalid token formats fail validation
t_shirt_size category and size must exist in active config T-shirt size Yes — unknown category/size fails resolution

Summary

Estimation method Required fields Distribution Good for
Explicit range (triangular) low, expected, high Triangular (bounded) Well-understood tasks with clear bounds
Explicit range (log-normal) low, expected, high, distribution: "lognormal" Shifted log-normal Exploratory tasks with open-ended risk
T-shirt size t_shirt_size Inherits project/task distribution after config lookup Relative estimation, early planning
Story points story_points Inherits project/task distribution after config lookup Agile teams using story point practices

All methods produce the same kind of output: a sampled duration for each iteration. The choice of method depends on what information the team is comfortable providing, not on any difference in simulation behavior.

\newpage