Multi-Phase (Two-Pass) Simulation

Multi-phase simulation is an advanced scheduling strategy for resource-constrained projects. When several tasks compete for the same limited pool of resources, the order in which they are dispatched to those resources can materially affect the projected completion date.

The standard scheduler uses a simple greedy policy: when multiple tasks become ready at the same moment it picks them in deterministic ID order. This works well when resources are abundant or contention is low. When resources are scarce and some tasks are strongly critical, a smarter ordering—one that dispatches the most critical tasks first—can reduce the median project duration and, more importantly, reduce tail-risk at the P80– P95 percentiles.

Two-pass simulation solves this problem with two consecutive simulation runs.

Only active with resource-constrained scheduling

Two-pass mode requires at least one named resource in your project file. If no resources are defined the engine falls back to the standard single-pass mode automatically.

How It Works

Pass 1 (baseline)          Pass 2 (priority-ordered)
───────────────────        ─────────────────────────
Greedy dispatch            Criticality-ranked dispatch
N = pass1_iterations       N = iterations (full run)

┌──────────┐               ┌──────────────────────────┐
│ Sample   │               │ Replay pass-1 durations  │  ← paired replay
│ durations│               │ (first pass1_iterations) │
└────┬─────┘               │ Sample fresh for the     │
     │                     │ remaining iterations     │
     ▼                     └───────────┬──────────────┘
┌──────────────┐                       │
│ Build        │                       ▼
│ criticality  │          ┌─────────────────────────┐
│ index CI(t)  │          │ Sort ready tasks by     │
│ per task     │─────────▶│ descending CI → earlier │
└──────────────┘          │ dispatch of critical    │
                          │ tasks                   │
                          └──────────┬──────────────┘
                          ┌─────────────────────────┐
                          │ TwoPassDelta:           │
                          │  pass-1 stats           │
                          │  pass-2 stats           │
                          │  Δ = pass-2 − pass-1    │
                          │  CI per task            │
                          └─────────────────────────┘

Pass 1 — criticality baseline
The engine runs pass1_iterations iterations using the standard greedy policy. Every iteration, it records which tasks appear on the critical path. The criticality index of each task is the fraction of pass-1 iterations in which it was critical (range 0 → 1). Task durations are also cached for paired replay.

Pass 2 — priority-ordered run
The engine runs the full --iterations run again. Whenever two or more tasks become ready at the same moment and there is a resource to claim, they are sorted by descending criticality index before dispatch. This ensures that pass-1 identified bottleneck tasks get resources first.

For the first pass1_iterations iterations, the exact same sampled durations from pass-1 are replayed (paired replay). This makes the comparison between pass-1 and pass-2 apples-to-apples: any difference in project duration is caused solely by the change in dispatch policy, not by different duration samples.

TwoPassDelta traceability
The results include a two_pass_traceability block in all output formats (console, JSON, CSV, HTML) with per-pass statistics and Δ values.

Basic Example

Project file

For this example we will use the provided examples/contention.yaml file with three tasks sharing one senior developer and a separate junior developer:

project:
  name: "contention-demo"
  start_date: "2025-03-01"
  hours_per_day: 8
  confidence_levels: [50, 80, 90, 95]

tasks:
  - id: "A1"
    name: "Spec review"
    estimate: { low: 9, expected: 10, high: 12 }
    resources: ["dev-senior"]

  - id: "A2"
    name: "Core implementation"
    estimate: { low: 13, expected: 15, high: 18 }
    dependencies: ["A1"]
    resources: ["dev-senior"]

  - id: "A3"
    name: "Code review"
    estimate: { low: 9, expected: 10, high: 12 }
    dependencies: ["A2"]
    resources: ["dev-senior"]

  - id: "B1"
    name: "Documentation"
    estimate: { low: 18, expected: 20, high: 24 }
    resources: ["dev-senior"]          # competes for dev-senior!
  - id: "B2"
    name: "User testing"
    estimate: { low: 9, expected: 10, high: 12 }
    dependencies: ["B1"]
    resources: ["dev-junior"]
  - id: "C1"
    name: "Integration"
    estimate: { low: 4, expected: 5, high: 7 }
    dependencies: ["A3", "B2"]
    resources: ["dev-junior"]
  - id: "C2"
    name: "Release"
    estimate: { low: 7, expected: 8, high: 10 }
    dependencies: ["C1"]
    resources: ["dev-junior"]

resources:
  - name: "dev-senior"
    experience_level: 3

  - name: "dev-junior"
    experience_level: 1

Single-pass run

mcprojsim % mcprojsim simulate examples/contention.yaml -n 1000 -t --seed 1234

Output excerpt:

=== Simulation Results ===

Calendar Time Statistical Summary:
┌──────────────────────────┬────────────────────────────────┐
│ Metric                   │ Value                          │
├──────────────────────────┼────────────────────────────────┤
│ Mean                     │ 567.49 hours (71 working days) │
│ Median (P50)             │ 559.94 hours                   │
│ Std Dev                  │ 13.64 hours                    │
└──────────────────────────┴────────────────────────────────┘

Calendar Time Confidence Intervals:
┌──────────────┬─────────┬────────────────┬────────────┐
│ Percentile   │   Hours │   Working Days │ Date       │
├──────────────┼─────────┼────────────────┼────────────┤
│ P50          │  559.94 │             70 │ 2025-06-06 │
│ P80          │  578.91 │             73 │ 2025-06-11 │
│ P90          │  580.6  │             73 │ 2025-06-11 │
│ P95          │  581.68 │             73 │ 2025-06-11 │
└──────────────┴─────────┴────────────────┴────────────┘
\newpage

Two-pass run

Add the --two-pass flag:

mcprojsim % mcprojsim simulate examples/contention.yaml -n 1000 --two-pass --pass1-iterations 500 -t --seed 1234

Output excerpt:

Pass 1: computing criticality indices
Progress: 100.0% (500/500)
Pass 2: priority-ordered scheduling
Progress: 100.0% (1000/1000)

=== Simulation Results ===

Calendar Time Statistical Summary:
┌──────────────────────────┬────────────────────────────────┐
│ Metric                   │ Value                          │
├──────────────────────────┼────────────────────────────────┤
│ Mean                     │ 470.91 hours (59 working days) │
│ Median (P50)             │ 463.49 hours                   │
│ Std Dev                  │ 13.28 hours                    │
└──────────────────────────┴────────────────────────────────┘

Calendar Time Confidence Intervals:
┌──────────────┬─────────┬────────────────┬────────────┐
│ Percentile   │   Hours │   Working Days │ Date       │
├──────────────┼─────────┼────────────────┼────────────┤
│ P50          │  463.49 │             58 │ 2025-05-21 │
│ P80          │  482.47 │             61 │ 2025-05-26 │
│ P90          │  484.08 │             61 │ 2025-05-26 │
│ P95          │  485.34 │             61 │ 2025-05-26 │
└──────────────┴─────────┴────────────────┴────────────┘

Two-Pass Scheduling Traceability:
┌──────────┬────────────────────┬─────────────────────┬─────────┐
│ Metric   │ Pass-1 iter: 500   │ Pass-2 iter: 1000   │ Delta   │
├──────────┼────────────────────┼─────────────────────┼─────────┤
│ Mean     │ 567.4h             │ 470.9h              │ -96.5h  │
│ P80      │ 578.9h             │ 482.5h              │ -96.4h  │
│ P95      │ 582.0h             │ 485.3h              │ -96.6h  │
└──────────┴────────────────────┴─────────────────────┴─────────┘

Resource wait delta: -121.1h

The two-pass run reduces the mean project duration from ~567 h to ~471 h (~12 working days) purely by prioritising the tasks that pass-1 identified as critical bottlenecks.

When Is Two-Pass Useful?

Two-pass simulation is most valuable when all of the following are true:

Condition Why it matters
Named resources are defined in the project file Without resources, dispatch order has no effect
At least two tasks compete for the same resource No contention → dispatch order is irrelevant
Some tasks have much higher criticality than others Uniform criticality → reordering has little effect
The project has more than ~5–10 tasks Very small projects often have no slack to reorder

Typical use-cases

  • Software delivery teams where one or two senior engineers are on the critical path and also reviewed by junior work items
  • Infrastructure projects where a specialist (network architect, DBA) is a shared bottleneck across multiple workstreams
  • Hardware/software co-design where a scarce test bench is contended between parallel integration streams
  • Any project where you suspect the default greedy schedule is sub-optimal

When two-pass has little effect

If every task has its own dedicated resource (no contention), the delta will be close to zero. Example with abundant-resources.yaml (each task on its own resource):

Two-Pass Scheduling Traceability:
  Pass-1 iterations: 300 | Pass-2 iterations: 500
  Mean: 189.6h (pass-1) → 189.2h (pass-2) [delta -0.3h]
  P80:  194.7h (pass-1) → 194.6h (pass-2) [delta -0.1h]
  P95:  197.1h (pass-1) → 196.8h (pass-2) [delta -0.3h]
  Resource wait delta: +0.0h

The near-zero delta confirms that two-pass adds no distortion when resources are not a bottleneck.

Configuration Reference

CLI flags

Flag Default Description
--two-pass off Enable two-pass mode for this run
--pass1-iterations N 1 000 Pass-1 iteration budget for criticality ranking

Both flags are accepted by the simulate command. --pass1-iterations requires --two-pass to have any effect.

# Basic two-pass run
mcprojsim simulate project.yaml --two-pass

# Fine-tuned: pass-1 with 2 000 iterations, pass-2 with 10 000
mcprojsim simulate project.yaml --two-pass --pass1-iterations 2000 -n 10000

# Export all formats
mcprojsim simulate project.yaml --two-pass -n 5000 -f json,csv,html -o report

Configuration file

You can set the assignment mode globally in your ~/.mcprojsim/configuration.yaml or any config file passed with --config:

constrained_scheduling:
  assignment_mode: criticality_two_pass   # default: greedy_single_pass
  pass1_iterations: 1000                  # default: 1000

With this config, every simulate invocation uses two-pass mode automatically for projects that have resources, with no need for the --two-pass flag.

\newpage

More Complex Example: Developer Allocation

Consider a project with three workstreams all sharing a DevOps engineer for deployment tasks:

project:
  name: "multi-stream-release"
  start_date: "2025-06-01"
  hours_per_day: 8
  confidence_levels: [50, 80, 90, 95]

tasks:
  # --- Stream A: Backend ---
  - id: "backend-dev"
    name: "Backend development"
    estimate: { low: 60, expected: 80, high: 120 }
    resources: ["backend-dev-1"]

  - id: "backend-deploy"
    name: "Backend deployment"
    estimate: { low: 8, expected: 12, high: 16 }
    dependencies: ["backend-dev"]
    resources: ["devops"]              # shared bottleneck

  # --- Stream B: Frontend ---
  - id: "frontend-dev"
    name: "Frontend development"
    estimate: { low: 40, expected: 60, high: 90 }
    resources: ["frontend-dev-1"]

  - id: "frontend-deploy"
    name: "Frontend deployment"
    estimate: { low: 6, expected: 8, high: 12 }
    dependencies: ["frontend-dev"]
    resources: ["devops"]              # shared bottleneck

# --- Stream C: Mobile ---
  - id: "mobile-dev"
    name: "Mobile development"
    estimate: { low: 80, expected: 100, high: 140 }
    resources: ["mobile-dev-1"]

  - id: "mobile-deploy"
    name: "Mobile deployment"
    estimate: { low: 8, expected: 10, high: 14 }
    dependencies: ["mobile-dev"]
    resources: ["devops"]              # shared bottleneck
  # --- Integration ---
  - id: "smoke-test"
    name: "Smoke test all streams"
    estimate: { low: 8, expected: 12, high: 20 }
    dependencies: ["backend-deploy", "frontend-deploy", "mobile-deploy"]
    resources: ["qa-1"]

  - id: "release"
    name: "Production release"
    estimate: { low: 4, expected: 6, high: 10 }
    dependencies: ["smoke-test"]
    resources: ["devops"]

resources:
  - name: "backend-dev-1"
    experience_level: 3

  - name: "frontend-dev-1"
    experience_level: 2

  - name: "mobile-dev-1"
    experience_level: 2

  - name: "devops"
    experience_level: 3

  - name: "qa-1"
    experience_level: 2

Run with two-pass to discover which deployment stream should be prioritised:

mcprojsim simulate multi-stream.yaml --two-pass --pass1-iterations 2000 \
  -n 10000 -t -f json,html -o multi-stream-report

The TwoPassDelta block in the JSON output will show which stream's deploy task had the highest criticality index in pass-1, and how much the end-to-end schedule improved once pass-2 gave that stream's DevOps slot priority.

\newpage

Output Formats

Console (-t table mode)

A Two-Pass Scheduling Traceability table is printed after the constrained diagnostics when --two-pass is active. The table shows pass-1, pass-2, and Δ values for Mean, P80, and P95. The resource wait delta is printed on a separate line below the table.

JSON export (-f json)

The two_pass_traceability key is always present. It is null for single-pass runs and an object for two-pass runs:

{
  "two_pass_traceability": {
    "enabled": true,
    "pass1_iterations": 500,
    "pass2_iterations": 1000,
    "ranking_method": "criticality_index",
    "pass1": {
      "mean_hours": 519.9,
      "p50_hours": 519.8,
      "p80_hours": 530.6,
      "p90_hours": 532.7,
      "p95_hours": 533.0,
      "resource_wait_hours": 212.2,
      "resource_utilization": 0.87,
      "calendar_delay_hours": 0.0
    },
    "pass2": {
      "mean_hours": 422.8,
      "p50_hours": 422.3,
      "p80_hours": 434.3,
      "p90_hours": 436.4,
      "p95_hours": 437.1,
      "resource_wait_hours": 90.2,
      "resource_utilization": 0.91,
      "calendar_delay_hours": 0.0
    },
    "delta": {
      "mean_hours": -97.0,
      "p50_hours": -97.5,
      "p80_hours": -96.3,
      "p90_hours": -96.3,
      "p95_hours": -95.9,
      "resource_wait_hours": -122.0,
      "resource_utilization": 0.04,
      "calendar_delay_hours": 0.0
    },
    "task_criticality_index": {
      "A1": 0.0,
      "A2": 0.0,
      "A3": 0.0,
      "B1": 1.0,
      "B2": 1.0,
      "C1": 1.0,
      "C2": 1.0
    }
  }
}

CSV export (-f csv)

A Two-Pass Scheduling Traceability section is appended after the constrained diagnostics block, followed by a Task Criticality Index (pass-1) section that lists each task's CI value.

HTML export (-f html)

The HTML report gains a Two-Pass Scheduling Traceability table with pass-1, pass-2, and Δ columns for each key metric, followed by a Task Criticality Index (Pass 1) table.


Choosing pass1_iterations

Pass-1 is used only to rank tasks; it does not directly affect the final results. A few practical guidelines:

Scenario Recommended pass1_iterations
Quick exploratory run 200–500
Standard analysis 500–2 000 (default 1 000)
Rigorous / publication-quality 2 000–5 000
Noisy project with many tasks 5 000+

The default of 1 000 is a good balance between ranking stability and computational cost for most projects. If you reduce pass1_iterations below 100 the engine logs a warning that the criticality indices may be noisy.

pass1_iterations is automatically capped to --iterations if it is larger.


Interpreting the Delta

The delta values tell you the effect of smarter dispatch on each reported metric, holding all other inputs constant:

Delta sign Meaning
Negative (e.g. -97 h) Pass-2 schedule is shorter → good, the reordering helped
Near zero No contention, or all tasks equally critical → reordering made no difference
Positive Unusual; could indicate that the pass-1 ranking was noisy (increase pass1_iterations)

A large negative delta on mean/P80 combined with a large negative delta on resource wait time is strong evidence that the project suffers from avoidable resource contention, and that assigning more resources or restructuring task ownership would reduce schedule risk.