Interpreting Results¶
After running a simulation, mcprojsim produces a set of statistics, percentiles, critical path data, and optionally an HTML report with a histogram and thermometer chart. This chapter explains what those outputs mean and how to use them for practical decision-making.
The output at a glance¶
A typical CLI run (using examples/sample_project.yaml) produces output like this:
mcprojsim, version 0.3.0
Progress: 100.0% (10000/10000)
Simulation time: 3.42 seconds
Peak simulation memory: 18.72 MiB
Max parallel tasks: 3
=== Simulation Results ===
Project: Customer Portal Redesign
Hours per Day: 8.0
Mean: 578.47 hours (73 working days)
Median (P50): 571.84 hours
Std Dev: 78.27 hours
Coefficient of Variation: 0.1353
Skewness: 0.4865
Excess Kurtosis: 0.2469
Confidence Intervals:
P25: 522.75 hours (66 working days) (2026-02-02)
P50: 571.84 hours (72 working days) (2026-02-10)
P75: 627.77 hours (79 working days) (2026-02-19)
P80: 642.81 hours (81 working days) (2026-02-23)
P85: 660.11 hours (83 working days) (2026-02-25)
P90: 682.94 hours (86 working days) (2026-03-02)
P95: 715.57 hours (90 working days) (2026-03-06)
P99: 790.61 hours (99 working days) (2026-03-19)
Effort Confidence Intervals:
P25: 854.12 person-hours (107 person-days)
P50: 910.15 person-hours (114 person-days)
P75: 972.47 person-hours (122 person-days)
P80: 992.18 person-hours (125 person-days)
P85: 1015.33 person-hours (127 person-days)
P90: 1046.80 person-hours (131 person-days)
P95: 1091.24 person-hours (137 person-days)
P99: 1182.57 person-hours (148 person-days)
Sensitivity Analysis (top contributors):
task_004: +0.4322
task_008: +0.3244
task_002: +0.3110
task_006: +0.2730
task_001: +0.1760
task_005: +0.1658
task_007: +0.0062
task_003: -0.0049
Schedule Slack:
task_008: 0.00 hours (Critical)
task_006: 0.00 hours (Critical)
task_005: 0.00 hours (Critical)
task_004: 0.00 hours (Critical)
task_001: 0.00 hours (Critical)
task_002: 0.00 hours (Critical)
task_003: 165.16 hours (165.2h buffer)
task_007: 355.57 hours (355.6h buffer)
Risk Impact Analysis:
task_001: mean=3.18h, triggers=19.9%, mean_when_triggered=16.00h
task_003: mean=5.84h, triggers=24.3%, mean_when_triggered=24.00h
task_004: mean=11.74h, triggers=29.3%, mean_when_triggered=40.00h
task_006: mean=11.13h, triggers=34.8%, mean_when_triggered=32.00h
task_008: mean=4.89h, triggers=20.4%, mean_when_triggered=24.00h
Most Frequent Critical Paths:
1. task_001 -> task_002 -> task_004 -> task_005 -> task_006 -> task_008
(10000/10000, 100.0%)
Staffing (based on mean effort): 3 people recommended (mixed team), 38 working days
Total effort: 910 person-hours (114 person-days) | Parallelism ratio: 1.6
No export formats specified. Use -f to export results to files.
Every number here comes from simulating your project thousands of times with different random samples. The results describe the distribution of outcomes, not a single prediction.
The sections below explain each part of this output in detail.
Output modes and flags that change what you see¶
Several simulate flags change which sections are printed:
| Flag | Effect on output |
|---|---|
--minimal |
Shows only core overview and confidence intervals; omits detailed analyses (sensitivity, slack, risk impact, etc.) |
--table |
Renders sections as ASCII tables instead of plain text lines |
--quiet, -q, -qq |
Reduces or suppresses normal console output |
--staffing |
Adds full per-profile staffing tables (senior, mixed, junior, plus custom profiles) |
--critical-paths N |
Changes how many full critical path sequences are listed |
--target-date YYYY-MM-DD |
Adds probability of finishing by that date |
--include-historic-base |
Adds Historic Base payload/sections in JSON/HTML exports (requires output format including json or html) |
Two additional flags affect output only when resource-constrained scheduling is active:
| Flag | Effect on output |
|---|---|
--two-pass |
Enables criticality two-pass scheduling |
--pass1-iterations |
Sets pass-1 sample size used for two-pass ranking |
Because of these switches, not every run prints every section shown in this chapter.
Project overview fields¶
At the top of simulation results, mcprojsim prints core context fields before detailed analyses.
ProjectHours per DayMax Parallel TasksSchedule Mode
Schedule Mode tells you whether the run used dependency-only scheduling or resource/calendar-constrained scheduling. Read all downstream sections in that context.
Understanding percentiles¶
Percentiles are the most actionable part of the output. Each percentile answers the question: "How many hours (or days) would be enough to finish the project X% of the time?"
| Percentile | Practical meaning |
|---|---|
| P50 | The median — half the simulated outcomes finished faster, half slower. This is an aggressive target; you have a coin-flip chance of meeting it. |
| P75 | Three out of four simulations finished by this point. A reasonable internal planning target for teams comfortable with some risk. |
| P80 | Four out of five simulations finished here. Often used as the default commitment for internal stakeholders. |
| P90 | Nine out of ten simulations finished. A common choice for external commitments and contractual deadlines. |
| P95 | Only 1 in 20 simulations exceeded this. A conservative target suitable for high-stakes commitments where a miss is costly. |
| P99 | Virtually worst-case. Useful for capacity planning or budget ceilings, but not a realistic daily target. |
Choosing the right percentile¶
There is no universally correct percentile. The right choice depends on the cost of being late versus the cost of over-committing:
- Low-stakes internal milestone: P75–P80 is usually sufficient. If you slip, you adjust.
- Customer-facing deadline: P85–P90 gives a meaningful safety margin without excessive padding.
- Contractual commitment with penalties: P90–P95 is appropriate when the consequence of a miss is significant.
- Budget ceiling or worst-case planning: P95–P99 helps answer "what's the most this could possibly cost?"
A useful rule of thumb: commit externally at the P85–P90 level, plan internally at P50, and track the gap between them. If the gap is large, your project has high uncertainty — which is itself valuable information.
Working days and delivery dates¶
Each percentile also shows working days (hours ÷ hours_per_day, rounded up) and a projected delivery date that counts forward from start_date, skipping weekends. These are calculated from the hours figure — they are not separate estimates.
Effort confidence intervals¶
The Effort Confidence Intervals section appears immediately after the calendar confidence intervals. While the calendar percentiles answer "how long will this project take?", the effort percentiles answer "how much total work will this project require?"
Effort Confidence Intervals:
P50: 910.15 person-hours (114 person-days)
P80: 992.18 person-hours (125 person-days)
P90: 1046.80 person-hours (131 person-days)
P95: 1091.24 person-hours (137 person-days)
What is total effort?¶
Total effort is the sum of all task durations in a single simulation iteration — the total person-hours of work required. This differs from calendar/elapsed time because tasks that run in parallel still each consume their full person-hours.
For example, if two 40-hour tasks run at the same time, the elapsed time is 40 hours but the total effort is 80 person-hours. In projects with high parallelism, effort is always larger than elapsed time.
Why effort varies across iterations¶
Each Monte Carlo iteration samples different task durations from the estimate ranges. Some iterations draw longer durations (more total work), others draw shorter ones. Risks that fire in some iterations add extra effort. The effort percentiles capture this variation:
- P50 effort: Half the simulations needed less than this much total work, half needed more.
- P80–P90 effort: A high-confidence estimate of total person-hours required.
- P95–P99 effort: Near-worst-case total work, driven by wide estimate ranges and risk events firing.
Effort vs. calendar time¶
The parallelism ratio connects the two:
$$ \text{Parallelism ratio} = \frac{\text{Mean total effort}}{\text{Mean elapsed time}} $$
A ratio of 1.0 means all tasks are serial (effort = elapsed time). A ratio above 1.0 means tasks overlap, so effort exceeds elapsed time. The sample output shows a parallelism ratio of 1.57, meaning about 57% more work is done than the wall clock suggests because of concurrent tasks.
Practical use¶
| Use case | Which metric to use |
|---|---|
| Scheduling and deadlines | Calendar confidence intervals (P80–P90 elapsed hours) |
| Budgeting and cost estimation | Effort confidence intervals (P80–P90 person-hours) |
| Staffing decisions | Effort percentiles tell you how many person-hours to fund; the staffing table maps that to team sizes |
| Comparing estimates to actuals | Track both: actual elapsed time against calendar P50, and actual time-sheet hours against effort P50 |
Minimum and maximum¶
In addition to mean/median/std-dev, the CLI also reports observed minimum and maximum simulated durations.
- Minimum is the fastest sampled project completion across iterations.
- Maximum is the slowest sampled completion.
These are useful for sanity checking tails, but they are sample extremes, not commitment targets. Use percentiles (P80/P90/P95) for planning decisions.
The effort summary has the same fields (minimum/maximum person-hours) for total work.
The thermometer chart¶
The HTML report includes two thermometers — vertical colour-coded bars showing elapsed time and effort (person-hours) at probability levels from 50% to 99%. They provide a quick visual: green zones are highly likely to succeed, orange zones are risky.
The colour transitions as a continuous gradient from dark orange (50%) to dark green (99%):
- Dark orange (50%–70%): aggressive targets. You are more likely than not to miss these.
- Olive/amber tones (75%–85%): moderate confidence. Reasonable for internal targets.
- Green → dark green (90%–99%): high confidence. Suitable for external commitments.
The colour thresholds are configurable via probability_red_threshold and probability_green_threshold in the project file.
Mean vs. median¶
The mean (average) and median (P50) are often close, but they diverge when the distribution is skewed — which it almost always is in software projects, because tasks tend to overrun more than they finish early.
- When mean > median, the distribution has a right tail (some iterations produced long durations pulling the average up). This is normal.
- A large gap between mean and median signals high asymmetry. It suggests a few bad-case scenarios are contributing disproportionately to the average.
For planning, the median is generally more useful than the mean. The mean can be distorted by outliers, while the median always represents the 50th-percentile outcome.
Standard deviation and coefficient of variation¶
The standard deviation measures the spread of outcomes in hours. By itself, the number is hard to interpret — 50 hours of spread means something different for a 100-hour project than for a 1000-hour one.
The coefficient of variation (CV) normalises the spread so that you can compare uncertainty across projects of different sizes.
Definition¶
$$ \text{CV} = \frac{\sigma}{\mu} $$
where $\sigma$ is the standard deviation and $\mu$ is the mean project duration.
Interpretation¶
| CV | Interpretation |
|---|---|
| < 0.15 | Low uncertainty — estimates are tight and risks are well-contained |
| 0.15–0.30 | Moderate uncertainty — typical for well-scoped projects with some unknowns |
| 0.30–0.50 | High uncertainty — wide estimate ranges or significant risk exposure |
| > 0.50 | Very high uncertainty — the project timeline is essentially unpredictable at this stage |
In the sample output, CV = 0.1353 indicates low uncertainty: the spread of outcomes is about 13.5% of the mean.
What to watch out for¶
- CV increasing across re-estimates: If the CV grows as you refine estimates, new information is revealing wider uncertainty than originally assumed. This is healthy — it means the model is becoming more honest.
- Very low CV (< 0.05): Suspiciously tight. Check whether estimate ranges are artificially narrow (e.g.,
minandmaxalmost equal) or whether risks have been omitted. - CV > 0.50: The schedule is so uncertain that committing to any specific date is risky. Consider breaking the project into phases and re-estimating each one.
Practical use¶
A high CV is not necessarily bad — it is honest. It tells you that the inputs contain wide estimate ranges, high-probability risks, or both. Narrowing the CV means improving the inputs: tightening estimates, reducing risk exposure, or breaking large tasks into better-understood pieces. Use the CV to compare uncertainty across different project proposals: a project with CV 0.40 carries much more schedule risk than one with CV 0.15, regardless of their absolute durations.
Skewness¶
Skewness measures how asymmetric the distribution of project durations is. In software projects, distributions almost always skew right: there are more ways for things to go wrong than to go better than planned.
Definition¶
$$ \text{Skewness} = \frac{1}{n} \sum_{i=1}^{n} \left( \frac{x_i - \mu}{\sigma} \right)^3 $$
A positive value means the distribution has a longer right tail (late finishes are further from the median than early finishes). A negative value means the opposite. Zero means perfect symmetry.
Interpretation¶
| Skewness | Meaning |
|---|---|
| ~ 0 | Roughly symmetric — early and late outcomes are about equally spread around the median |
| 0.1–0.5 | Mild right skew — a slight tendency toward late outcomes, which is typical |
| 0.5–1.0 | Moderate right skew — the mean is noticeably higher than the median; a few bad scenarios are pulling the average up |
| > 1.0 | Strong right skew — significant tail risk; worst-case outcomes are much worse than typical outcomes |
In the sample output, Skewness = 0.4865 indicates moderate right skew: some iterations hit notably longer durations than the median, but the effect is not extreme.
What to watch out for¶
- Skewness > 1.0: The project has significant tail risk. The mean is a poor planning target — use the median (P50) instead, and pay close attention to P90/P95.
- Negative skewness: Unusual in project estimation. It may indicate that
maxestimates are too conservative relative tomin, or that uncertainty factors are compressing durations at the high end. - Skewness combined with high CV: When both are high, the project has both wide variance and a long tail. This is a red flag for external commitments.
Practical use¶
When skewness is positive, the mean overstates a "typical" outcome. Prefer the median for internal planning. The gap between mean and median quantifies how much the tail is pulling the average: a gap of 10+ hours suggests meaningful tail risk that should be communicated to stakeholders.
Excess kurtosis¶
Excess kurtosis describes the "tailedness" of the distribution — whether extreme outcomes (very early or very late finishes) are more or less likely than a normal distribution would predict.
Definition¶
$$ \text{Excess Kurtosis} = \frac{1}{n} \sum_{i=1}^{n} \left( \frac{x_i - \mu}{\sigma} \right)^4 - 3 $$
The $-3$ subtracts the kurtosis of a normal distribution, so that a normal distribution has excess kurtosis of zero.
Interpretation¶
| Excess kurtosis | Meaning |
|---|---|
| ~ 0 | Tail behaviour similar to a normal distribution |
| > 0 (leptokurtic) | Heavier tails — extreme outcomes are more frequent than normal. Surprises (both good and bad) happen more often |
| < 0 (platykurtic) | Lighter tails — outcomes are more concentrated around the mean. Fewer surprises |
In the sample output, Excess Kurtosis = 0.2469 is slightly positive, meaning the tails are marginally heavier than a normal distribution — a small number of iterations produced notably long (or short) durations.
What to watch out for¶
- Kurtosis > 2: Heavy tails. The P95 and P99 values may be much higher than P90 suggests. Check the high percentiles carefully before making commitments at those levels.
- Kurtosis < −1: Very light tails. This may indicate that estimate ranges are too narrow or that the model lacks risks that could cause extreme outcomes.
- Kurtosis combined with high skewness: When both are high and positive, the distribution has a fat right tail — rare but severe overruns are plausible.
Practical use¶
Excess kurtosis guides how much buffer to add between your planning target and your worst-case commitment. When kurtosis is high, the gap between P90 and P99 is larger than usual, so committing at P90 leaves more residual risk than it would for a normal-tailed distribution. Conversely, negative kurtosis means outcomes are bunched together and P90 commitments are safer than they might first appear.
Sensitivity analysis¶
The sensitivity analysis section ranks tasks by how strongly their duration influences the total project duration. It answers the question: "Which task's estimate uncertainty matters most to the overall schedule?"
Definition¶
Sensitivity is measured using Spearman's rank correlation coefficient ($\rho$) between each task's sampled durations and the project's total duration across all iterations:
$$ \rho = 1 - \frac{6 \sum d_i^2}{n(n^2 - 1)} $$
where $d_i$ is the difference between the rank of the task duration and the rank of the project duration in iteration $i$, and $n$ is the number of iterations.
The sign indicates the direction of the relationship. A positive value (the norm) means that when this task takes longer, the project takes longer. The magnitude (0 to 1) indicates the strength.
Interpretation¶
| Correlation | Meaning |
|---|---|
| > +0.5 | Strong positive driver — this task's variance is a major contributor to project variance |
| +0.2 to +0.5 | Moderate driver — contributes meaningfully to schedule uncertainty |
| −0.1 to +0.2 | Weak or negligible — the task has little influence on overall duration |
| < −0.1 | Inverse relationship — unusual and worth investigating (possibly a non-critical task that shares resources) |
In the sample output, task_004: +0.4322 is the strongest driver, meaning its duration variance contributes the most to the spread of project outcomes. Tasks near zero (like task_007: +0.0062) have essentially no influence — even large changes to their estimates would not move the project schedule.
What to watch out for¶
- Several tasks above +0.3: Schedule uncertainty is spread across multiple tasks. Reducing variance on any single task has limited effect — you need to address several.
- One dominant task (> +0.7): This task essentially controls the schedule. Focus estimation refinement and risk mitigation there first.
- Negative correlations: Usually means the task is on a non-critical branch. When it runs long, a different branch becomes critical, and the total project time may stay the same or even decrease (rare).
Practical use¶
Use sensitivity to prioritise where to invest in better estimates. Spending a day refining the estimate for a +0.45 task reduces overall schedule uncertainty far more than refining a +0.02 task. In the HTML report, the sensitivity analysis appears as a tornado chart for visual comparison.
Reading the tornado chart¶
The tornado chart is a ranked horizontal bar chart of task sensitivity values.
How to read it:
- Bar length = influence strength: longer bars mean stronger influence on total project duration.
- Signed value = direction: bars to the right of zero indicate positive correlation (longer task -> longer project), while bars to the left indicate negative correlation (uncommon inverse relationship).
- Top bars = highest priority: tasks are sorted by absolute correlation, so the most influential tasks are grouped as the key schedule drivers.
- Colour = direction cue: positive and negative bars use different colours to make direction easier to scan quickly.
Scope note:
- The chart is a prioritisation view, not a full dump of every task. It shows the most influential tasks (up to 15) to keep the chart readable.
Interpretation rule of thumb:
- Start at the top bar and work downward.
- Focus first on tasks that are both long bars and operationally important (for example, low slack or high risk impact).
- Treat small bars near zero as lower-leverage targets, even if their raw estimates look uncertain.
Schedule slack¶
Schedule slack (also called total float) shows how much each task can be delayed without delaying the overall project. It is calculated using a backward-pass Critical Path Method (CPM) and then averaged across all Monte Carlo iterations.
Definition¶
For each task, the total float is:
$$ \text{Slack} = LS - ES $$
where $LS$ is the latest start time (computed via the backward pass from the project end) and $ES$ is the earliest start time (from the forward pass). The value reported is the mean slack across all simulation iterations.
Interpretation¶
- 0.00 hours (Critical): The task is on the critical path in most or all iterations. Any delay to this task delays the project.
- Positive slack (buffer): The task can overrun by up to this many hours without affecting the project delivery date. The larger the buffer, the less you need to worry about this task.
In the sample output, task_003 has 165.16 hours of slack and task_007 has 355.57 hours — these tasks could each overrun significantly without moving the project deadline. Meanwhile, six tasks show zero slack, confirming they are consistently on the critical path.
What to watch out for¶
- All tasks showing zero slack: The project is a single serial chain with no parallelism. Any task delay equals a project delay. Consider restructuring dependencies to create parallel paths.
- Very small slack (< 8 hours / 1 day): The task is almost critical. It appears on the critical path in some iterations. Treat it with similar urgency to zero-slack tasks.
- Slack changing across runs: If the same task has very different slack with different seeds, the critical path is unstable — the project has competing bottleneck paths, and which one dominates depends on which sampled durations happen to be long.
Practical use¶
Slack tells you where you have scheduling flexibility. Tasks with large buffers are safe to deprioritise, start later, or assign to less experienced team members. Tasks with zero slack are where delays are most costly — prioritise them in resource allocation, assign your strongest people, and mitigate their risks first.
Risk impact analysis¶
The risk impact analysis section shows how much each task's risks contribute to the schedule across all simulation iterations. This goes beyond listing risks in the project file — it shows what actually happened during the simulation.
Reported metrics¶
For each task that has risks defined, three values are reported:
| Metric | Definition |
|---|---|
| mean | Average risk impact across all iterations (in hours), including iterations where the risk did not trigger: $\text{mean} = \frac{1}{n} \sum_{i=1}^{n} \text{impact}_i$ |
| triggers | Trigger rate — the fraction of iterations where at least one risk on this task fired: $\text{triggers} = \frac{\text{count}(\text{impact} > 0)}{n}$ |
| mean_when_triggered | Average impact in only the iterations where a risk actually fired: $\text{mean_when_triggered} = \frac{\sum_{i : \text{impact}_i > 0} \text{impact}_i}{\text{count}(\text{impact} > 0)}$ |
Interpretation¶
In the sample output:
This means: in 29.3% of the 10,000 iterations, at least one of task_004's risks fired. When they did, they added an average of 40 hours. Across all iterations (including the 70.7% where nothing happened), the average impact was 11.74 hours.
The gap between mean and mean_when_triggered reveals whether a risk is a frequent nuisance or a rare catastrophe:
- High trigger rate, low impact when triggered: A frequent but manageable disruption. The overall mean is close to
mean_when_triggered. - Low trigger rate, high impact when triggered: A "black swan" event. The overall mean looks low, but when it hits, it hits hard. These deserve contingency planning.
What to watch out for¶
- High trigger rate (> 50%): The risk is more likely than not. Consider whether it should be modelled as part of the base estimate rather than as a risk.
- Large
mean_when_triggeredon a critical-path task: This combination has the highest potential to blow the schedule. Iftask_004is critical (zero slack) and adds 40 hours when its risk fires, that is a full working week added to the project almost a third of the time. - Tasks with no risk output: These tasks have no risks defined. If they have high sensitivity scores, consider whether risks were overlooked.
Practical use¶
Combine risk impact analysis with sensitivity and slack to decide where to act:
- If a task has high sensitivity + zero slack + high trigger rate → top priority for risk mitigation.
- If a task has high
mean_when_triggeredbut low trigger rate → have a contingency plan ready, but don't rearrange the whole schedule for it. - If a task has large slack → its risks are mostly absorbed by the buffer. Monitor, but don't prioritise.
Critical path analysis¶
What is the critical path?¶
The critical path is the longest chain of dependent tasks that determines when the project finishes. If any task on the critical path takes longer, the whole project takes longer. Tasks not on the critical path have slack — they can overrun without affecting the delivery date, up to a point.
Why Monte Carlo gives multiple critical paths¶
In a deterministic schedule there is one critical path. In a Monte Carlo simulation, each iteration samples different task durations, so the critical path can shift. A task that is critical in one iteration may have slack in another.
mcprojsim tracks this across all iterations and reports:
-
Criticality index per task — the fraction of iterations where that task appeared on a critical path. A criticality of 0.85 means the task was critical in 85% of simulations.
-
Most frequent critical path sequences — the full path (e.g., A → C → E) and how often it occurred.
How to use criticality¶
- Criticality > 0.7: This task is almost always on the critical path. It is a bottleneck. Focus risk mitigation, staffing, and management attention here.
- Criticality 0.3–0.7: Sometimes critical, sometimes not. Worth monitoring, but not the primary bottleneck.
- Criticality < 0.3: Rarely critical. This task has significant slack in most scenarios.
If multiple tasks share high criticality, the project has several competing bottleneck paths. That actually reduces schedule risk compared to a single dominant path, because no one task controls the outcome.
Max parallel tasks¶
The Max parallel tasks line reports the highest number of tasks that were scheduled to run at the same time in any single simulation iteration. The scheduler places every task at the earliest moment its dependencies allow, so two tasks without a dependency relationship can overlap.
How it is calculated¶
After each iteration schedules tasks, a sweep-line algorithm scans through the start and end events of every task. A task is considered active during the half-open interval $[\text{start}, \text{end})$, so a task ending at the exact moment another begins does not count as concurrent. The peak concurrent count from each iteration is recorded, and the overall maximum across all iterations is reported.
Interpretation¶
| Value | Meaning |
|---|---|
| 1 | All tasks form a single serial chain — no parallelism. |
| 2–3 | Limited parallelism. A small team can handle the concurrent work. |
| 4+ | Significant parallelism. Verify that you actually have enough people or capacity to run this many tasks simultaneously. |
In the sample output, Max parallel tasks: 3 means the scheduler assumed up to three tasks running at the same time in at least one iteration.
Why this matters¶
Interpretation depends on schedule mode:
- In dependency-only mode, peak parallelism reflects structural parallelism implied by dependencies and assumes unlimited resource capacity.
- In resource-constrained mode, scheduling already accounts for resource availability and calendars.
Use this number as a sanity check:
- If dependency-only mode and max parallel tasks <= team size: the unconstrained parallelism assumption is plausible.
- If dependency-only mode and max parallel tasks > team size: the run is optimistic relative to your real capacity.
- If resource-constrained mode: combine this with constrained diagnostics (below) to understand where waiting and calendar effects are occurring.
Constrained schedule diagnostics¶
When resource/calendar constraints are active, the CLI adds:
- Average Resource Wait (hours)
- Effective Resource Utilization
- Calendar Delay Contribution (hours)
These quantify how much elapsed time comes from waiting for available resources and working-time calendars, not just raw task effort.
Use these diagnostics to decide whether to add capacity, rebalance assignments, or adjust calendars.
Two-pass scheduling traceability¶
When --two-pass is enabled (or equivalent config mode is active), output may include a traceability block comparing pass-1 and pass-2 results.
Reported deltas include:
- mean duration (
pass-1 -> pass-2) - P80 duration (
pass-1 -> pass-2) - P95 duration (
pass-1 -> pass-2) - resource wait delta
This helps explain whether two-pass prioritization materially improved (or worsened) schedule outcomes for your project structure.
Target-date probability¶
If you pass --target-date YYYY-MM-DD, the CLI prints the estimated probability of finishing by that date.
This converts an external deadline question into a direct probabilistic statement and is often the clearest communication artifact for stakeholders.
Staffing recommendations¶
The staffing advisory appears at the bottom of every simulation run. It answers the question: "Given this project's parallelism and effort, how many people should work on it?"
The advisory line¶
Staffing (based on mean effort): 3 people recommended (mixed team), 38 working days
Total effort: 910 person-hours (114 person-days) | Parallelism ratio: 1.6
This tells you:
- Recommended team size: The team size that achieves the shortest calendar duration for this profile. The search stops at the first local minimum: if adding one more person would make the schedule longer (because communication overhead outweighs the extra capacity — a manifestation of Brooks's Law), the current size is chosen. If all team sizes within the display range keep improving, the largest shown size is recommended.
- Experience profile: The profile used for the quick advisory ("mixed" by default). See below for a comparison of all profiles.
- Working days: Estimated calendar duration with the recommended team, accounting for communication overhead.
- Total effort: The sum of mean task durations, measured in person-hours. This is the amount of work regardless of how many people do it.
- Parallelism ratio: Total effort divided by critical-path duration. A ratio of 1.0 means the project is entirely serial; higher values indicate potential for parallel work.
- Effort basis: Shown in parentheses after "Staffing". By default the analysis is based on mean effort and elapsed time. Set
staffing.effort_percentilein configuration (e.g.80) to use a specific percentile instead — this produces more conservative recommendations for risk-averse planning.
The --staffing flag¶
Pass --staffing to see a detailed table for each experience profile:
=== Staffing Analysis ===
--- senior ---
Team Size Eff. Capacity Working Days Delivery Date Efficiency
1 1.00 114 2026-06-15 36.9%
2 1.92 60 2026-03-27 70.9%
3* 2.76 42 2026-03-02 100.0% <-- recommended
--- mixed ---
Team Size Eff. Capacity Working Days Delivery Date Efficiency
1 0.85 134 2026-07-14 37.9%
2 1.60 72 2026-04-13 71.2%
3* 2.24 51 2026-03-16 100.0% <-- recommended
--- junior ---
Team Size Eff. Capacity Working Days Delivery Date Efficiency
1 0.65 176 2026-10-08 39.7%
2 1.20 96 2026-06-12 73.0%
3* 1.64 70 2026-05-06 100.0% <-- recommended
Each column is explained below.
Communication overhead model (Brooks's Law)¶
Adding people to a project increases communication overhead — a concept famously expressed in Fred Brooks's The Mythical Man-Month. mcprojsim models this with a simple formula:
$$ E(n) = n \cdot \max(p_{\min},\; 1 - c \cdot (n - 1)) \cdot f $$
where:
| Symbol | Meaning | Default values |
|---|---|---|
| $n$ | Team size | — |
| $c$ | Per-person communication overhead | 0.04 (senior), 0.06 (mixed), 0.08 (junior) |
| $f$ | Productivity factor for the experience profile | 1.00, 0.85, 0.65 |
| $p_{\min}$ | Floor on individual productivity | 0.25 |
| $E(n)$ | Effective capacity in "ideal-person" units | — |
The individual productivity of one person on an $n$-person team is $\max(p_{\min},\; 1 - c \cdot (n - 1))$. This decreases linearly with team size until it hits the floor.
Calendar duration is then:
$$ T(n) = \max!\left(T_{\text{CP}},\; \frac{W}{E(n)}\right) $$
where $W$ is total effort (person-hours) and $T_{\text{CP}}$ is the critical-path duration — an irreducible lower bound that no amount of parallelism can shorten.
Understanding the table columns¶
| Column | Meaning |
|---|---|
| Team Size | Number of people |
| Eff. Capacity | $E(n)$ — the team's output in "ideal-person" equivalents after overhead |
| Working Days | Calendar working days at this team size |
| Delivery Date | Projected date (weekends excluded), or blank if no start_date |
| Efficiency | How close this team size is to the fastest possible schedule for this profile, expressed as a percentage. Calculated as $\text{min calendar hours} / \text{this row's calendar hours}$. 100 % means this team achieves the minimum calendar duration (it is the optimal size or tied at the critical-path floor). Values below 100 % indicate the team is either too small (parallelism is underutilised) or too large (communication overhead has exceeded the gain from extra capacity). |
The row marked with * or <-- recommended is the optimal team size for that profile.
Experience profiles¶
Three built-in profiles model different team compositions:
| Profile | Productivity factor ($f$) | Overhead ($c$) | Description |
|---|---|---|---|
| senior | 1.00 | 0.04 | Experienced team — high output, low overhead |
| mixed | 0.85 | 0.06 | Typical blend of senior and junior — moderate overhead |
| junior | 0.65 | 0.08 | Less experienced team — higher coordination cost |
Profiles are fully configurable. In a YAML config, override or add profiles under staffing.experience_profiles:
staffing:
effort_percentile: 80 # use P80 effort for conservative staffing (omit for mean)
min_individual_productivity: 0.25
experience_profiles:
senior:
productivity_factor: 1.0
communication_overhead: 0.04
mixed:
productivity_factor: 0.85
communication_overhead: 0.06
my_custom_team:
productivity_factor: 0.90
communication_overhead: 0.05
Choosing an effort basis¶
By default, the staffing model operates on mean values — mean total effort and mean elapsed (critical-path) time. This gives a "most likely" recommendation.
For risk-averse planning, set staffing.effort_percentile to a higher percentile (e.g. 80 or 90). When set, the model uses:
- PN total effort instead of mean total effort
- PN elapsed time instead of mean elapsed time
This results in more people or more calendar time, but protects against schedules that only work in the average case. The chosen basis is always shown in the output so there is no ambiguity.
| Setting | Behaviour | Use when |
|---|---|---|
| (omitted) | Mean effort and elapsed time | You want the most likely recommendation |
effort_percentile: 50 |
Median effort / elapsed time | Similar to mean for symmetric distributions |
effort_percentile: 80 |
P80 effort / elapsed time | Moderate risk aversion |
effort_percentile: 90 |
P90 effort / elapsed time | Conservative / high-stakes projects |
How efficiency is calculated¶
The Efficiency column answers: "How close is this team size to the best achievable schedule for this profile?"
$$ \text{Efficiency}(n) = \frac{T_{\min}}{T(n)} $$
where $T_{\min}$ is the shortest calendar duration found across all team sizes for this profile, and $T(n)$ is the calendar duration at team size $n$.
- 100 %: This team size achieves the minimum calendar duration. The recommended team (
*) always shows 100 %. - Below 100 %: The schedule is longer than the optimum. Two different situations can cause this:
- Too few people (left of the optimal): The project is effort-bound — parallelism is underutilised and adding more people would shorten the schedule.
- Too many people (right of the optimal): The project is in the Brooks's Law diminishing-returns zone — communication overhead now outweighs the benefit of extra capacity, so the schedule actually lengthens.
Interpreting the profile tables together¶
A typical profile shows a "U-shaped" efficiency curve (when viewed from left to right): low efficiency at team size 1, rising as team size grows, peaking at 100 % at the recommended size, then potentially falling if the overhead regime kicks in.
| Efficiency pattern | What it means |
|---|---|
| Monotonically rising to 100 % (no drop) | The project never enters the overhead regime within the displayed range. All shown team sizes are effort-bound; the last is the fastest. |
| Peaks at 100 % then drops | The optimal team is in the middle of the range. Teams beyond the peak are actively slowed by overhead. |
| All rows near 100 % | The project is dominated by the critical path; adding people makes little difference to calendar time. |
- Recommended size = 1: The project is almost entirely serial (parallelism ratio near 1.0) or the total effort is small. Adding people just adds overhead.
- Recommended size = max parallel tasks: The project has enough parallelism to keep everyone busy. This is the ideal scenario.
- Senior team recommends more people than junior: A senior team has lower overhead per person, so it can grow larger before the overhead outweighs the benefit.
- Efficiency drops below 70%: Adding more people is subject to strongly diminishing returns. Consider splitting the project into independent work streams instead.
Caveats¶
- The model assumes all team members can work on any task. In practice, specialisation may constrain who does what.
- It does not account for ramp-up time: a new team member joining mid-project may take weeks to reach full productivity.
- The communication overhead is linear in team size. Real-world overhead grows faster (some models use $n(n-1)/2$ communication channels); the linear model is a conservative simplification.
- The simulation already assumes unlimited parallelism, so the staffing recommendation does not change the simulated durations — it is an advisory layer on top of the existing results.
Combining the analyses¶
The real power of these metrics comes from reading them together. Here is a decision framework:
| Situation | Action |
|---|---|
| High sensitivity + zero slack + high risk trigger rate | Top priority. This task drives the schedule, sits on the critical path, and frequently gets hit by risk events. Invest in mitigation, tighter estimates, or splitting the task. |
| High sensitivity + zero slack + low risk trigger rate | Monitor closely. The task drives the schedule through estimate variance, not risk. Focus on refining the estimate range. |
| High sensitivity + large slack | Unusual. The task's duration varies a lot but it isn't critical. Investigate whether dependencies are correctly modelled. |
| Low sensitivity + zero slack | The task is on the critical path but doesn't contribute much variance. It is a stable bottleneck — duration is predictable but the path still runs through it. |
| Low sensitivity + large slack | Low priority. This task has both predictable duration and scheduling flexibility. |
Reducing volatility¶
If the spread between P50 and P90 is uncomfortably wide, consider:
- Splitting large tasks: A single task with
low: 5, high: 40contributes more variance than two tasks withlow: 3, high: 20each, especially when they are on different dependency paths. - Tightening estimate ranges: If subject-matter experts can narrow the gap between
minandmaxafter investigation, uncertainty drops directly. - Mitigating high-impact risks: Removing or reducing the probability of risks on critical tasks has the largest effect.
- Adding parallel paths: Restructuring dependencies so that fewer tasks are in a single sequential chain reduces the chance of cascading delays.
- Addressing high-sensitivity tasks first: Use the sensitivity analysis to focus effort where it matters most.
Limitations of the simulation¶
Monte Carlo simulation is a powerful tool, but it has boundaries. Understanding them prevents over-reliance on the numbers.
What the simulation does well¶
- Quantifies the range of plausible outcomes given uncertain inputs
- Identifies which tasks and risks contribute most to schedule uncertainty
- Provides probabilistic confidence levels instead of false-precision single-number estimates
- Handles complex dependency structures and mixed estimation methods
What the simulation does not do¶
-
It does not improve bad inputs. If your estimate ranges are systematically optimistic — if the real
maxis higher than what you entered — the simulation will be optimistic too. The output is only as good as the input. -
It assumes task independence. Each task's duration is sampled independently. In reality, if one task overruns because the technology is harder than expected, related tasks may also overrun. The simulation does not model these correlations.
-
Dependency-only runs ignore resource constraints. If you do not model
resources/calendars, parallelism is constrained only by dependencies. For resource-constrained planning, use the constrained scheduling inputs and read the constrained diagnostics section. -
It does not model learning or momentum. Teams often speed up as they gain context, or slow down from fatigue. The simulation treats each task in isolation.
-
Risks are binary. Each risk either fires or doesn't, at a fixed probability. In reality, risk severity exists on a spectrum and probabilities shift as the project evolves.
Calibration matters¶
The most useful thing you can do over time is calibrate: compare the simulation's P50 and P90 with actual outcomes, and adjust your estimation habits accordingly. If your P90 is consistently exceeded, your max values are too low. If P50 is consistently beaten, your min values may be too conservative — or your uncertainty factors are inflating estimates.
Quick reference¶
| Output | What it tells you | Primary use |
|---|---|---|
| P50 (median) | The 50/50 point | Internal planning baseline |
| P80–P90 | High-confidence estimates | External commitments |
| Std dev / CV | How spread out the outcomes are | Gauging overall uncertainty |
| Skewness | How asymmetric the distribution is (tail risk) | Deciding between mean and median for planning |
| Excess kurtosis | Whether extreme outcomes are more/less likely than normal | Sizing the buffer between P90 and P99 |
| Sensitivity | Which tasks drive overall schedule variance | Prioritising estimation and risk-mitigation effort |
| Schedule slack | How much buffer each task has before delaying the project | Resource allocation and task prioritisation |
| Risk impact | How often and how much each task's risks fire | Identifying high-impact risk events to mitigate |
| Criticality index | How often a task is on the critical path | Focusing management attention |
| Critical path sequences | Which chains of tasks dominate | Dependency restructuring |
| Max parallel tasks | Peak number of tasks running simultaneously | Validating resource assumptions |
| Effort confidence intervals | Total person-hours at each probability level | Budgeting, cost estimation, staffing |
| Staffing advisory | Recommended team size per experience profile | Team sizing, hiring decisions |
| Thermometer | Visual probability-to-effort mapping | Stakeholder communication |
| Delivery dates | Calendar dates at each percentile | Scheduling and milestone setting |
Sprint-planning mode outputs (when enabled)¶
If a project uses sprint-planning mode, output sections differ from dependency-schedule runs and include sprint-specific summaries such as:
- Sprint planning summary
- Sprint count statistical summary
- Sprint count confidence intervals
- Optional historical diagnostics (series, ratios, correlations)
- Burn-up percentiles
Treat these as the sprint-forecast analogue of calendar/effort percentiles in dependency-schedule mode.