Constrained Scheduling¶
This chapter shows how to model and run resource- and calendar-constrained simulations in mcprojsim, starting from a simple project and building up to a full-featured example.
Constrained scheduling is activated automatically when the validated project has resources available for assignment—either from a top-level resources section or from project.team_size > 0 (which auto-generates default resources up to that size).
What constrained scheduling changes¶
In dependency-only mode, tasks start as soon as dependencies are complete.
In constrained mode, task start and completion times also depend on:
- resource availability,
- resource experience and productivity,
- task-level resource requirements,
- working calendars and holidays,
- planned absences and sickness probability.
The CLI and exporters report this explicitly via:
Schedule Mode(dependency_onlyorresource_constrained),- constrained diagnostics (resource wait time, utilization, calendar delay contribution).
Suggested reading path¶
For first-time readers, follow this order:
- Example 1 through Example 6 (progressive walkthrough)
team_sizerules (reference section)- CLI/config tuning knobs (
--two-pass,--pass1-iterations, and config defaults)
If you already know the core flow, jump directly to the team_size and two-pass sections.
How team_size affects scheduling (reference)¶
team_size and top-level resources interact during validation before simulation starts.
Current rules:
team_sizeomitted or0: use only explicitly listedresources.team_size > 0and explicit resources exceedteam_size: validation error.team_size > 0and explicit resources are fewer thanteam_size: default resources are auto-created up toteam_size.- no
resourcesand noteam_size(orteam_size: 0): scheduler remains dependency-only.
Example A: tasks only (no team_size)¶
project:
name: "Team Size Demo"
start_date: "2026-04-01"
hours_per_day: 8
tasks:
- id: "task_001"
name: "Task 1"
estimate: { low: 8, expected: 16, high: 24 }
- id: "task_002"
name: "Task 2"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
Example B: same tasks, with team_size¶
project:
name: "Team Size Demo"
start_date: "2026-04-01"
hours_per_day: 8
team_size: 10
tasks:
- id: "task_001"
name: "Task 1"
estimate: { low: 8, expected: 16, high: 24 }
- id: "task_002"
name: "Task 2"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
Sample output excerpt (seed 42, 200 iterations):
team_size: 10 auto-creates 10 default resources, so this run is constrained.
Example C: explicit resources + team_size (smaller than resources)¶
project:
name: "Team Size + Resources"
start_date: "2026-04-01"
hours_per_day: 8
team_size: 1
tasks:
- id: "task_001"
name: "Task 1"
estimate: { low: 8, expected: 16, high: 24 }
- id: "task_002"
name: "Task 2"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
resources:
- name: "alice"
experience_level: 3
productivity_level: 1.0
- name: "bob"
experience_level: 2
productivity_level: 0.9
Sample output excerpt:
Error: Invalid project file format: 1 validation error for Project
Value error, team_size is smaller than explicitly specified resources: team_size=1, resources=2
Example D: explicit resources + team_size (larger than resources)¶
Same as Example C but with team_size: 20.
Sample output excerpt (same run settings):
team_size: 20 is valid here: two explicit resources are kept and the remaining capacity is auto-filled with defaults.
Interpretation and policy¶
team_sizeis a capacity target when greater than zero.- Explicit
resourcescan be combined withteam_size, but they must not exceed it. - If explicit resources are fewer than
team_size, generated defaults fill the gap. - If both are omitted (or
team_size: 0with no resources), the run is dependency-only.
Example 1: Baseline (dependency-only)¶
Start with a minimal project that has dependencies but no resource section.
project:
name: "Onboarding Portal"
start_date: "2026-04-01"
hours_per_day: 8
tasks:
- id: "task_001"
name: "Requirements"
estimate: { low: 8, expected: 16, high: 24 }
- id: "task_002"
name: "Implementation"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
Run:
You should see Schedule Mode: dependency_only.
Sample output excerpt (seed 42, 200 iterations):
Schedule Mode: dependency_only
Calendar Time Confidence Intervals:
P50: 129.86 hours (17 working days) (2026-04-24)
P90: 155.97 hours (20 working days) (2026-04-29)
P99: 170.61 hours (22 working days) (2026-05-01)
Resource fields introduced in this chapter¶
Before Example 2, here is a quick reference for the resources fields used throughout the walkthrough.
| Field | Required | Default | What it controls |
|---|---|---|---|
name |
No | auto-generated (resource_001, ...) |
Stable resource identifier used by tasks |
availability |
No | 1.0 |
Fractional availability (for example 0.8 for 80%) |
experience_level |
No | 2 |
Skill level (1, 2, or 3) used with min_experience_level |
productivity_level |
No | 1.0 |
Relative throughput multiplier (valid range 0.1 to 2.0) |
calendar |
No | default |
Which calendar (calendars[*].id) the resource follows |
sickness_prob |
No | 0.0 |
Per-working-day sickness probability for stochastic absence |
planned_absence |
No | [] |
Explicit non-working dates for that resource |
First two fields introduced in Example 2¶
experience_level: the resource's capability tier (1,2,3).productivity_level: how quickly the resource converts effort into progress relative to baseline1.0.
In Example 2, Alice (3, 1.0) is modeled as more senior baseline-capacity, while Bob (2, 0.9) is slightly less productive.
Task fields related to resources introduced in this chapter¶
| Field | Required | Default | What it controls |
|---|---|---|---|
resources |
No | (all pool resources) | Explicit list of resource names eligible for this task; omit to allow any available resource |
max_resources |
No | 1 | Maximum number of resources assigned to a task |
min_experience_level |
No | 1 | Minimum experience_level a resource must have to be eligible for this task |
max_resources semantics (important)¶
max_resources is an upper bound on concurrent assignees for a task, but the
scheduler also applies an automatic practical cap.
- If
resourceslists multiple names andmax_resourcesis smaller than that list, only up tomax_resourcesresources are assigned at task start.
Automatic practical cap heuristic:
granularity_cap = max(1, floor(task_effort_hours / 16.0))coordination_cap = 3practical_cap = min(granularity_cap, coordination_cap)
Effective assignment count at start is:
min(max_resources, practical_cap, currently_available_eligible_resources)
- If
max_resourcesis omitted, the default is1.
Why this exists:
- It prevents unrealistic compression of small tasks (for example, assigning eight people to an ~8–24 hour task).
- It keeps behavior deterministic while limiting over-parallelization on large tasks.
Practical examples:
- Task effort
8h→granularity_cap = max(1, floor(8/16)) = 1→ at most 1 assignee. - Task effort
24h→granularity_cap = max(1, floor(24/16)) = 1→ at most 1 assignee. - Task effort
80h→granularity_cap = floor(80/16) = 5, but coordination cap limits to 3.
Why these constants were selected:
MIN_EFFORT_PER_ASSIGNEE_HOURS = 16.0means each assignee should have about two working days of effort before the heuristic adds another concurrent person.MAX_ASSIGNEES_PER_TASK = 3is a hard global coordination ceiling, even for very large tasks.- The pair balances realism and runtime simplicity: the scheduler remains deterministic and fast while avoiding implausible near-linear speedups.
How the 16.0 and 3 factors shape assignment¶
The heuristic has two stages:
- Granularity stage (
16.0) - Compute
floor(task_effort_hours / 16.0). - This is a rough "how many meaningful chunks" estimate for parallel work.
-
max(1, ...)guarantees at least one assignee. -
Coordination stage (
3) - Apply
min(granularity_cap, 3). - This caps parallelism to avoid unrealistic linear speedup from many assignees.
Combined effect by effort range:
0 <= effort < 32hours: practical cap is132 <= effort < 48hours: practical cap is2effort >= 48hours: practical cap is3(ceiling reached)
So 16.0 controls when you earn additional assignees, while 3 controls the maximum you can ever get from the heuristic.
How this interacts with actual assignment¶
The practical cap is only one limiter. Final assigned count is:
min(max_resources, practical_cap, currently_available_eligible_resources)
Implications:
- If
max_resourcesis lower than the practical cap, task-level config wins. - If fewer eligible resources are free, availability wins.
- If both are high, heuristic limits still apply (
3max from practical cap).
Quick examples:
- Effort
40h,max_resources: 5, 4 eligible free resources:granularity_cap = floor(40/16) = 2,practical_cap = 2-> assign up to2. - Effort
80h,max_resources: 2, 5 eligible free resources:granularity_cap = 5,practical_cap = 3, thenmax_resourceslowers final cap to2. - Effort
120h,max_resources: 5, only 1 eligible free resource: heuristic allows3, but availability lowers final assignment to1.
If you need stricter or looser behavior in your environment, these constants can be adjusted in the scheduler implementation and validated with scenario-specific simulations.
Assignment timing model¶
Resource assignment is performed only when the task starts.
- Assigned resources remain fixed for that task run (non-preemptive execution).
- The scheduler does not swap or add resources mid-task.
Start-now vs wait-for-more-resources behavior¶
Current automatic assignment is greedy:
- If at least one eligible resource is available, the task can start immediately.
- The scheduler does not delay task start to wait for additional resources that might become available later.
This is a deliberate trade-off for deterministic and scalable simulation on large projects. This avoids combinatorial explosion and keeps runtime predictable for large projects. It is a heuristic, not globally optimal schedule optimization.
Example 2: Add resources (single-pass automatic assignment)¶
Now add a top-level resources section. This enables constrained scheduling.
project:
name: "Onboarding Portal"
start_date: "2026-04-01"
hours_per_day: 8
tasks:
- id: "task_001"
name: "Requirements"
estimate: { low: 8, expected: 16, high: 24 }
- id: "task_002"
name: "Implementation"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
resources:
- name: "alice"
experience_level: 3
productivity_level: 1.0
- name: "bob"
experience_level: 2
productivity_level: 0.9
Run:
Sample output excerpt (seed 42, 200 iterations):
Schedule Mode: resource_constrained
Calendar Time Confidence Intervals:
P50: 529.86 hours (67 working days) (2026-07-03)
P90: 651.97 hours (82 working days) (2026-07-24)
P99: 698.61 hours (88 working days) (2026-08-03)
Constrained Schedule Diagnostics:
Calendar Delay Contribution: 404.16 hours
How resources are used in Example 2¶
In this example, tasks do not define tasks[*].resources, so each ready task can use the full resource pool:
alicebob
Assignment behavior in this case is:
- A task becomes eligible only after all dependencies are finished.
- If the task has no explicit
resourceslist, the scheduler considers all project resources. - Resources already busy on other tasks are not available (a resource can only work on one task at a time).
- The task receives up to
max_resourcesresources (default is1if omitted). - If no eligible resource is free, the task waits; this contributes to
Average Resource Waitin diagnostics.
Because max_resources defaults to 1, each task in Example 2 is effectively assigned one resource at a time unless you override it on the task.
Why experience_level and productivity_level matter here¶
experience_levelon each resource is matched against taskmin_experience_level(default task minimum is1).productivity_levelaffects effective capacity, so two resources with different productivity can produce different calendar durations even for the same effort.
\newpage
Making assignment explicit (optional)¶
If you want explicit control instead of automatic pooling, set tasks[*].resources:
tasks:
- id: "task_001"
name: "Requirements"
estimate: { low: 8, expected: 16, high: 24 }
resources: ["alice"]
- id: "task_002"
name: "Implementation"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
resources: ["alice", "bob"]
max_resources: 2
In that explicit form, only listed resources are considered for each task.
Look for:
Schedule Mode: resource_constrainedConstrained Schedule Diagnostics- Average Resource Wait (hours)
- Effective Resource Utilization
- Calendar Delay Contribution (hours)
\newpage
Example 3: Add working calendars¶
Attach resources to calendars and define working patterns.
project:
name: "Onboarding Portal"
start_date: "2026-04-01"
hours_per_day: 8
tasks:
- id: "task_001"
name: "Requirements"
estimate: { low: 8, expected: 16, high: 24 }
- id: "task_002"
name: "Implementation"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_001"]
resources:
- name: "alice"
calendar: "default"
experience_level: 3
productivity_level: 1.0
- name: "bob"
calendar: "part_time"
experience_level: 2
productivity_level: 0.9
calendars:
- id: "default"
work_hours_per_day: 8
work_days: [1, 2, 3, 4, 5]
holidays: ["2026-04-10"]
- id: "part_time"
work_hours_per_day: 6
work_days: [1, 2, 3, 4]
holidays: []
This introduces calendar-driven delays automatically (weekends, holidays, shorter days).
\newpage
Sample output excerpt (seed 42, 200 iterations):
Schedule Mode: resource_constrained
Calendar Time Confidence Intervals:
P50: 553.86 hours (70 working days) (2026-07-08)
P90: 675.97 hours (85 working days) (2026-07-29)
P99: 722.61 hours (91 working days) (2026-08-06)
Constrained Schedule Diagnostics:
Calendar Delay Contribution: 437.28 hours
Compared with Example 2, the added holiday and part-time calendar increase calendar-time percentiles and calendar-delay contribution.
Quick comparison (Examples 1 → 3)¶
The table below compares calendar-time percentiles from the sample runs above (seed 42, 200 iterations):
| Example | Schedule Mode | P50 (hours) | P90 (hours) | P99 (hours) |
|---|---|---|---|---|
| Example 1 (dependency-only) | dependency_only |
129.86 | 155.97 | 170.61 |
| Example 2 (resources only) | resource_constrained |
529.86 | 651.97 | 698.61 |
| Example 3 (resources + calendars) | resource_constrained |
553.86 | 675.97 | 722.61 |
This progression highlights how resource constraints and then calendar constraints increase elapsed calendar time, even when effort distributions are unchanged.
Example 4: Add sickness and planned absence¶
Sickness has three related configuration layers:
constrained_scheduling.sickness_probis the default per-resource sickness probability used when a resource omitssickness_prob,resources[*].sickness_probcontrols/overrides probability for that specific resource,sprint_defaults.sickness.duration_log_muandsprint_defaults.sickness.duration_log_sigmacontrol the shared log-normal duration model used when sickness occurs.
Explicit days off are set with planned_absence.
resources:
- name: "alice"
calendar: "default"
experience_level: 3
productivity_level: 1.0
sickness_prob: 0.02
planned_absence: ["2026-04-22"]
- name: "bob"
calendar: "part_time"
experience_level: 2
productivity_level: 0.9
sickness_prob: 0.04
planned_absence: ["2026-04-15", "2026-04-16"]
Note
resources[*].sickness_prob is configured in the project file per resource. If omitted, constrained scheduling falls back to constrained_scheduling.sickness_prob from the config file. If neither is set, the effective default remains 0.0.
Optional config for default sickness probability¶
With this setting:
- resources with explicit
sickness_probkeep their own value, - resources without
sickness_probuse0.03, - omitting this config block keeps the legacy
0.0default.
Optional config for sickness duration¶
If you want the constrained scheduler to assume shorter or longer sickness episodes, add this to your config file and run with --config:
This does not change who gets sick. It changes how long an absence tends to last once a sickness event occurs.
Note
The duration parameters (duration_log_mu and duration_log_sigma) are configured once under sprint_defaults.sickness and apply to both constrained scheduling and sprint planning. This ensures consistent absence duration modeling across both forecasting modes. Sickness probabilities, however, have separate mode-specific defaults: constrained_scheduling.sickness_prob (constrained mode only) and sprint_defaults.sickness.probability_per_person_per_week (sprint planning only).
Example 5: Add task-level resource constraints¶
Use task fields to control assignment behavior:
resources: restrict eligible resources by name,max_resources: cap parallel resources assigned to a task,min_experience_level: minimum allowed experience (1,2,3).
tasks:
- id: "task_003"
name: "Data migration"
estimate: { low: 24, expected: 40, high: 64 }
dependencies: ["task_002"]
resources: ["alice"]
max_resources: 1
min_experience_level: 3
- id: "task_004"
name: "System testing"
estimate: { low: 16, expected: 24, high: 40 }
dependencies: ["task_003"]
resources: ["alice", "bob"]
max_resources: 2
min_experience_level: 2
Compact recap: how assignment works in Example 5¶
task_003can only usealice(resources: ["alice"]) and is capped at one resource (max_resources: 1).task_004can use eitheraliceorbob, and can run with up to two resources in parallel (max_resources: 2) when both are available.min_experience_levelfilters the eligible set before assignment (for example, tasks requiring3cannot use level-2resources).- If fewer resources are available than requested by
max_resources, the task starts with what is available (if at least one eligible resource exists) and continues with reduced effective capacity.
This is the first point in the walkthrough where max_resources is actively overridden above the default (1) to allow multi-resource task execution.
\newpage
Example 6: Full constrained project (final build-up)¶
This example combines core project fields, risks, uncertainty factors, resource constraints, calendars, absences, and sickness.
project:
name: "Commerce Platform Upgrade"
description: "Backend modernization with staged rollout"
start_date: "2026-05-04"
confidence_levels: [50, 80, 90, 95]
hours_per_day: 8
probability_red_threshold: 0.5
probability_green_threshold: 0.9
project_risks:
- id: "risk_vendor"
name: "Vendor API latency"
probability: 0.2
impact: 16
impact_unit: "hours"
tasks:
- id: "task_001"
name: "Architecture design"
estimate: { low: 16, expected: 24, high: 40 }
uncertainty_factors:
team_experience: medium
technical_complexity: medium
- id: "task_002"
name: "Core implementation"
estimate: { low: 80, expected: 120, high: 180 }
dependencies: ["task_001"]
resources: ["alice", "bob", "carol"]
max_resources: 2
min_experience_level: 2
risks:
- id: "risk_rework"
name: "Unexpected rework"
probability: 0.25
impact: 24
impact_unit: "hours"
- id: "task_003"
name: "Migration"
estimate: { low: 40, expected: 64, high: 96 }
dependencies: ["task_002"]
resources: ["alice"]
max_resources: 1
min_experience_level: 3
- id: "task_004"
name: "Verification and rollout"
estimate: { low: 24, expected: 40, high: 64 }
dependencies: ["task_003"]
resources: ["alice", "bob", "carol"]
max_resources: 2
resources:
- name: "alice"
calendar: "default"
availability: 1.0
experience_level: 3
productivity_level: 1.1
sickness_prob: 0.02
planned_absence: ["2026-05-15"]
- name: "bob"
calendar: "default"
availability: 0.8
experience_level: 2
productivity_level: 1.0
sickness_prob: 0.03
- name: "carol"
calendar: "part_time"
availability: 0.75
experience_level: 2
productivity_level: 0.9
sickness_prob: 0.04
planned_absence: ["2026-06-01", "2026-06-02"]
calendars:
- id: "default"
work_hours_per_day: 8
work_days: [1, 2, 3, 4, 5]
holidays: ["2026-05-25"]
- id: "part_time"
work_hours_per_day: 6
work_days: [1, 2, 3, 4]
holidays: []
Run and export all formats:
mcprojsim validate constrained-full.yaml
mcprojsim simulate constrained-full.yaml \
--iterations 30000 \
--seed 42 \
--table \
--critical-paths 5 \
-f json,csv,html \
-o results/constrained-full
Single-pass vs double-pass assignment¶
Single-pass automatic assignment (available)¶
Current constrained scheduling uses deterministic single-pass assignment while respecting dependencies, resource eligibility, calendars, and absences.
You use it by defining top-level resources (and optionally calendars). No extra CLI flag is required.
Double-pass criticality assignment (available)¶
Double-pass criticality-prioritized scheduling is available via CLI and config.
How it works:
- Pass 1 runs greedy scheduling for a subset of iterations to estimate task criticality.
- Pass 2 re-runs constrained scheduling using criticality ranking as dispatch priority.
- Final summary metrics come from pass 2, with a two-pass traceability delta in CLI and exports.
CLI usage:
Config usage:
Notes:
--two-passoverrides config and enablescriticality_two_passfor that run.--pass1-iterationsis capped to total simulation iterations.- If
pass1_iterationsis small, criticality ranking may be noisy.
\newpage
CLI options most relevant to constrained runs¶
Use these with mcprojsim simulate:
| Option | Why it matters for constrained scheduling |
|---|---|
-n, --iterations |
More iterations stabilize constrained diagnostics and tail percentiles |
-s, --seed |
Makes resource/sickness-driven runs reproducible |
-c, --config |
Apply custom uncertainty and output/reporting defaults |
--two-pass |
Enable criticality two-pass constrained scheduling for this run |
--pass1-iterations |
Set pass-1 sample budget for criticality ranking in two-pass mode |
--critical-paths |
Show more critical-path sequences for bottleneck analysis |
-t, --table |
Easier reading of diagnostics and interval tables |
-f json,csv,html |
Export constrained diagnostics to all report channels |
-o |
Keep scenario outputs organized for side-by-side comparison |
--target-date |
Evaluate on-time probability against a concrete deadline |
Where to configure constrained behavior¶
In the project file (primary for constrained scheduling)¶
resources[*].availabilityresources[*].productivity_levelresources[*].experience_levelresources[*].calendarresources[*].sickness_probresources[*].planned_absencecalendars[*].work_hours_per_daycalendars[*].work_dayscalendars[*].holidaystasks[*].resourcestasks[*].max_resourcestasks[*].min_experience_level
In the config file (--config)¶
Use config files for simulation/reporting defaults and shared stochastic model parameters. They do not replace per-resource sickness probabilities in the project file, but they can now define the shared sickness-duration distribution used by constrained scheduling.
Example:
constrained_scheduling:
sickness_prob: 0.03
assignment_mode: criticality_two_pass
pass1_iterations: 1500
simulation:
default_iterations: 30000
output:
critical_path_report_limit: 5
histogram_bins: 80
staffing:
effort_percentile: 80
sprint_defaults:
sickness:
duration_log_mu: 1.10
duration_log_sigma: 0.90
constrained_scheduling.assignment_mode supports:
greedy_single_pass(default)criticality_two_pass
constrained_scheduling.pass1_iterations controls pass-1 ranking depth when two-pass mode is active.
Related chapters¶
- Project Files for full schema reference
- Running Simulations for command reference
- Interpreting Results for diagnostics interpretation
- Multi-Phase (Two-Pass) Simulation for criticality-prioritized scheduling