Constrained Scheduling

This chapter shows how to model and run resource- and calendar-constrained simulations in mcprojsim, starting from a simple project and building up to a full-featured example.

Constrained scheduling is activated automatically when the validated project has resources available for assignment—either from a top-level resources section or from project.team_size > 0 (which auto-generates default resources up to that size).

What constrained scheduling changes

In dependency-only mode, tasks start as soon as dependencies are complete.

In constrained mode, task start and completion times also depend on:

  • resource availability,
  • resource experience and productivity,
  • task-level resource requirements,
  • working calendars and holidays,
  • planned absences and sickness probability.

The CLI and exporters report this explicitly via:

  • Schedule Mode (dependency_only or resource_constrained),
  • constrained diagnostics (resource wait time, utilization, calendar delay contribution).

Suggested reading path

For first-time readers, follow this order:

  1. Example 1 through Example 6 (progressive walkthrough)
  2. team_size rules (reference section)
  3. CLI/config tuning knobs (--two-pass, --pass1-iterations, and config defaults)

If you already know the core flow, jump directly to the team_size and two-pass sections.

How team_size affects scheduling (reference)

team_size and top-level resources interact during validation before simulation starts.

Current rules:

  • team_size omitted or 0: use only explicitly listed resources.
  • team_size > 0 and explicit resources exceed team_size: validation error.
  • team_size > 0 and explicit resources are fewer than team_size: default resources are auto-created up to team_size.
  • no resources and no team_size (or team_size: 0): scheduler remains dependency-only.

Example A: tasks only (no team_size)

project:
  name: "Team Size Demo"
  start_date: "2026-04-01"
  hours_per_day: 8

tasks:
  - id: "task_001"
    name: "Task 1"
    estimate: { low: 8, expected: 16, high: 24 }
  - id: "task_002"
    name: "Task 2"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]

Example B: same tasks, with team_size

project:
  name: "Team Size Demo"
  start_date: "2026-04-01"
  hours_per_day: 8
  team_size: 10

tasks:
  - id: "task_001"
    name: "Task 1"
    estimate: { low: 8, expected: 16, high: 24 }
  - id: "task_002"
    name: "Task 2"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]

Sample output excerpt (seed 42, 200 iterations):

Schedule Mode: resource_constrained
Median (P50): 529.86 hours

team_size: 10 auto-creates 10 default resources, so this run is constrained.

Example C: explicit resources + team_size (smaller than resources)

project:
  name: "Team Size + Resources"
  start_date: "2026-04-01"
  hours_per_day: 8
  team_size: 1

tasks:
  - id: "task_001"
    name: "Task 1"
    estimate: { low: 8, expected: 16, high: 24 }
  - id: "task_002"
    name: "Task 2"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]

resources:
  - name: "alice"
    experience_level: 3
    productivity_level: 1.0
  - name: "bob"
    experience_level: 2
    productivity_level: 0.9

Sample output excerpt:

Error: Invalid project file format: 1 validation error for Project
  Value error, team_size is smaller than explicitly specified resources: team_size=1, resources=2

Example D: explicit resources + team_size (larger than resources)

Same as Example C but with team_size: 20.

Sample output excerpt (same run settings):

Schedule Mode: resource_constrained
Median (P50): 529.86 hours

team_size: 20 is valid here: two explicit resources are kept and the remaining capacity is auto-filled with defaults.

Interpretation and policy

  • team_size is a capacity target when greater than zero.
  • Explicit resources can be combined with team_size, but they must not exceed it.
  • If explicit resources are fewer than team_size, generated defaults fill the gap.
  • If both are omitted (or team_size: 0 with no resources), the run is dependency-only.

Example 1: Baseline (dependency-only)

Start with a minimal project that has dependencies but no resource section.

project:
  name: "Onboarding Portal"
  start_date: "2026-04-01"
  hours_per_day: 8

tasks:
  - id: "task_001"
    name: "Requirements"
    estimate: { low: 8, expected: 16, high: 24 }

  - id: "task_002"
    name: "Implementation"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]

Run:

mcprojsim simulate baseline.yaml --seed 42 --table

You should see Schedule Mode: dependency_only.

Sample output excerpt (seed 42, 200 iterations):

Schedule Mode: dependency_only
Calendar Time Confidence Intervals:
  P50: 129.86 hours (17 working days)  (2026-04-24)
  P90: 155.97 hours (20 working days)  (2026-04-29)
  P99: 170.61 hours (22 working days)  (2026-05-01)

Resource fields introduced in this chapter

Before Example 2, here is a quick reference for the resources fields used throughout the walkthrough.

Field Required Default What it controls
name No auto-generated (resource_001, ...) Stable resource identifier used by tasks
availability No 1.0 Fractional availability (for example 0.8 for 80%)
experience_level No 2 Skill level (1, 2, or 3) used with min_experience_level
productivity_level No 1.0 Relative throughput multiplier (valid range 0.1 to 2.0)
calendar No default Which calendar (calendars[*].id) the resource follows
sickness_prob No 0.0 Per-working-day sickness probability for stochastic absence
planned_absence No [] Explicit non-working dates for that resource

First two fields introduced in Example 2

  • experience_level: the resource's capability tier (1, 2, 3).
  • productivity_level: how quickly the resource converts effort into progress relative to baseline 1.0.

In Example 2, Alice (3, 1.0) is modeled as more senior baseline-capacity, while Bob (2, 0.9) is slightly less productive.

Field Required Default What it controls
resources No (all pool resources) Explicit list of resource names eligible for this task; omit to allow any available resource
max_resources No 1 Maximum number of resources assigned to a task
min_experience_level No 1 Minimum experience_level a resource must have to be eligible for this task

max_resources semantics (important)

max_resources is an upper bound on concurrent assignees for a task, but the scheduler also applies an automatic practical cap.

  • If resources lists multiple names and max_resources is smaller than that list, only up to max_resources resources are assigned at task start.

Automatic practical cap heuristic:

  • granularity_cap = max(1, floor(task_effort_hours / 16.0))
  • coordination_cap = 3
  • practical_cap = min(granularity_cap, coordination_cap)

Effective assignment count at start is:

min(max_resources, practical_cap, currently_available_eligible_resources)

  • If max_resources is omitted, the default is 1.

Why this exists:

  • It prevents unrealistic compression of small tasks (for example, assigning eight people to an ~8–24 hour task).
  • It keeps behavior deterministic while limiting over-parallelization on large tasks.

Practical examples:

  • Task effort 8hgranularity_cap = max(1, floor(8/16)) = 1 → at most 1 assignee.
  • Task effort 24hgranularity_cap = max(1, floor(24/16)) = 1 → at most 1 assignee.
  • Task effort 80hgranularity_cap = floor(80/16) = 5, but coordination cap limits to 3.

Why these constants were selected:

  • MIN_EFFORT_PER_ASSIGNEE_HOURS = 16.0 means each assignee should have about two working days of effort before the heuristic adds another concurrent person.
  • MAX_ASSIGNEES_PER_TASK = 3 is a hard global coordination ceiling, even for very large tasks.
  • The pair balances realism and runtime simplicity: the scheduler remains deterministic and fast while avoiding implausible near-linear speedups.

How the 16.0 and 3 factors shape assignment

The heuristic has two stages:

  1. Granularity stage (16.0)
  2. Compute floor(task_effort_hours / 16.0).
  3. This is a rough "how many meaningful chunks" estimate for parallel work.
  4. max(1, ...) guarantees at least one assignee.

  5. Coordination stage (3)

  6. Apply min(granularity_cap, 3).
  7. This caps parallelism to avoid unrealistic linear speedup from many assignees.

Combined effect by effort range:

  • 0 <= effort < 32 hours: practical cap is 1
  • 32 <= effort < 48 hours: practical cap is 2
  • effort >= 48 hours: practical cap is 3 (ceiling reached)

So 16.0 controls when you earn additional assignees, while 3 controls the maximum you can ever get from the heuristic.

How this interacts with actual assignment

The practical cap is only one limiter. Final assigned count is:

min(max_resources, practical_cap, currently_available_eligible_resources)

Implications:

  • If max_resources is lower than the practical cap, task-level config wins.
  • If fewer eligible resources are free, availability wins.
  • If both are high, heuristic limits still apply (3 max from practical cap).

Quick examples:

  • Effort 40h, max_resources: 5, 4 eligible free resources: granularity_cap = floor(40/16) = 2, practical_cap = 2 -> assign up to 2.
  • Effort 80h, max_resources: 2, 5 eligible free resources: granularity_cap = 5, practical_cap = 3, then max_resources lowers final cap to 2.
  • Effort 120h, max_resources: 5, only 1 eligible free resource: heuristic allows 3, but availability lowers final assignment to 1.

If you need stricter or looser behavior in your environment, these constants can be adjusted in the scheduler implementation and validated with scenario-specific simulations.

Assignment timing model

Resource assignment is performed only when the task starts.

  • Assigned resources remain fixed for that task run (non-preemptive execution).
  • The scheduler does not swap or add resources mid-task.

Start-now vs wait-for-more-resources behavior

Current automatic assignment is greedy:

  • If at least one eligible resource is available, the task can start immediately.
  • The scheduler does not delay task start to wait for additional resources that might become available later.

This is a deliberate trade-off for deterministic and scalable simulation on large projects. This avoids combinatorial explosion and keeps runtime predictable for large projects. It is a heuristic, not globally optimal schedule optimization.

Example 2: Add resources (single-pass automatic assignment)

Now add a top-level resources section. This enables constrained scheduling.

project:
  name: "Onboarding Portal"
  start_date: "2026-04-01"
  hours_per_day: 8

tasks:
  - id: "task_001"
    name: "Requirements"
    estimate: { low: 8, expected: 16, high: 24 }

  - id: "task_002"
    name: "Implementation"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]

resources:
  - name: "alice"
    experience_level: 3
    productivity_level: 1.0

  - name: "bob"
    experience_level: 2
    productivity_level: 0.9

Run:

mcprojsim simulate resources-basic.yaml --seed 42 --table

Sample output excerpt (seed 42, 200 iterations):

Schedule Mode: resource_constrained
Calendar Time Confidence Intervals:
  P50: 529.86 hours (67 working days)  (2026-07-03)
  P90: 651.97 hours (82 working days)  (2026-07-24)
  P99: 698.61 hours (88 working days)  (2026-08-03)

Constrained Schedule Diagnostics:
  Calendar Delay Contribution: 404.16 hours

How resources are used in Example 2

In this example, tasks do not define tasks[*].resources, so each ready task can use the full resource pool:

  • alice
  • bob

Assignment behavior in this case is:

  1. A task becomes eligible only after all dependencies are finished.
  2. If the task has no explicit resources list, the scheduler considers all project resources.
  3. Resources already busy on other tasks are not available (a resource can only work on one task at a time).
  4. The task receives up to max_resources resources (default is 1 if omitted).
  5. If no eligible resource is free, the task waits; this contributes to Average Resource Wait in diagnostics.

Because max_resources defaults to 1, each task in Example 2 is effectively assigned one resource at a time unless you override it on the task.

Why experience_level and productivity_level matter here

  • experience_level on each resource is matched against task min_experience_level (default task minimum is 1).
  • productivity_level affects effective capacity, so two resources with different productivity can produce different calendar durations even for the same effort.

\newpage

Making assignment explicit (optional)

If you want explicit control instead of automatic pooling, set tasks[*].resources:

tasks:
  - id: "task_001"
    name: "Requirements"
    estimate: { low: 8, expected: 16, high: 24 }
    resources: ["alice"]

  - id: "task_002"
    name: "Implementation"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]
    resources: ["alice", "bob"]
    max_resources: 2

In that explicit form, only listed resources are considered for each task.

Look for:

  • Schedule Mode: resource_constrained
  • Constrained Schedule Diagnostics
  • Average Resource Wait (hours)
  • Effective Resource Utilization
  • Calendar Delay Contribution (hours)

\newpage

Example 3: Add working calendars

Attach resources to calendars and define working patterns.

project:
  name: "Onboarding Portal"
  start_date: "2026-04-01"
  hours_per_day: 8

tasks:
  - id: "task_001"
    name: "Requirements"
    estimate: { low: 8, expected: 16, high: 24 }
  - id: "task_002"
    name: "Implementation"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_001"]

resources:
  - name: "alice"
    calendar: "default"
    experience_level: 3
    productivity_level: 1.0
  - name: "bob"
    calendar: "part_time"
    experience_level: 2
    productivity_level: 0.9

calendars:
  - id: "default"
    work_hours_per_day: 8
    work_days: [1, 2, 3, 4, 5]
    holidays: ["2026-04-10"]

  - id: "part_time"
    work_hours_per_day: 6
    work_days: [1, 2, 3, 4]
    holidays: []

This introduces calendar-driven delays automatically (weekends, holidays, shorter days).

\newpage

Sample output excerpt (seed 42, 200 iterations):

Schedule Mode: resource_constrained
Calendar Time Confidence Intervals:
  P50: 553.86 hours (70 working days)  (2026-07-08)
  P90: 675.97 hours (85 working days)  (2026-07-29)
  P99: 722.61 hours (91 working days)  (2026-08-06)

Constrained Schedule Diagnostics:
  Calendar Delay Contribution: 437.28 hours

Compared with Example 2, the added holiday and part-time calendar increase calendar-time percentiles and calendar-delay contribution.

Quick comparison (Examples 1 → 3)

The table below compares calendar-time percentiles from the sample runs above (seed 42, 200 iterations):

Example Schedule Mode P50 (hours) P90 (hours) P99 (hours)
Example 1 (dependency-only) dependency_only 129.86 155.97 170.61
Example 2 (resources only) resource_constrained 529.86 651.97 698.61
Example 3 (resources + calendars) resource_constrained 553.86 675.97 722.61

This progression highlights how resource constraints and then calendar constraints increase elapsed calendar time, even when effort distributions are unchanged.

Example 4: Add sickness and planned absence

Sickness has three related configuration layers:

  • constrained_scheduling.sickness_prob is the default per-resource sickness probability used when a resource omits sickness_prob,
  • resources[*].sickness_prob controls/overrides probability for that specific resource,
  • sprint_defaults.sickness.duration_log_mu and sprint_defaults.sickness.duration_log_sigma control the shared log-normal duration model used when sickness occurs.

Explicit days off are set with planned_absence.

resources:
  - name: "alice"
    calendar: "default"
    experience_level: 3
    productivity_level: 1.0
    sickness_prob: 0.02
    planned_absence: ["2026-04-22"]

  - name: "bob"
    calendar: "part_time"
    experience_level: 2
    productivity_level: 0.9
    sickness_prob: 0.04
    planned_absence: ["2026-04-15", "2026-04-16"]

Note

resources[*].sickness_prob is configured in the project file per resource. If omitted, constrained scheduling falls back to constrained_scheduling.sickness_prob from the config file. If neither is set, the effective default remains 0.0.

Optional config for default sickness probability

constrained_scheduling:
  sickness_prob: 0.03

With this setting:

  • resources with explicit sickness_prob keep their own value,
  • resources without sickness_prob use 0.03,
  • omitting this config block keeps the legacy 0.0 default.

Optional config for sickness duration

If you want the constrained scheduler to assume shorter or longer sickness episodes, add this to your config file and run with --config:

sprint_defaults:
  sickness:
    duration_log_mu: 1.10
    duration_log_sigma: 0.90

This does not change who gets sick. It changes how long an absence tends to last once a sickness event occurs.

Note

The duration parameters (duration_log_mu and duration_log_sigma) are configured once under sprint_defaults.sickness and apply to both constrained scheduling and sprint planning. This ensures consistent absence duration modeling across both forecasting modes. Sickness probabilities, however, have separate mode-specific defaults: constrained_scheduling.sickness_prob (constrained mode only) and sprint_defaults.sickness.probability_per_person_per_week (sprint planning only).

Example 5: Add task-level resource constraints

Use task fields to control assignment behavior:

  • resources: restrict eligible resources by name,
  • max_resources: cap parallel resources assigned to a task,
  • min_experience_level: minimum allowed experience (1, 2, 3).
tasks:
  - id: "task_003"
    name: "Data migration"
    estimate: { low: 24, expected: 40, high: 64 }
    dependencies: ["task_002"]
    resources: ["alice"]
    max_resources: 1
    min_experience_level: 3

  - id: "task_004"
    name: "System testing"
    estimate: { low: 16, expected: 24, high: 40 }
    dependencies: ["task_003"]
    resources: ["alice", "bob"]
    max_resources: 2
    min_experience_level: 2

Compact recap: how assignment works in Example 5

  • task_003 can only use alice (resources: ["alice"]) and is capped at one resource (max_resources: 1).
  • task_004 can use either alice or bob, and can run with up to two resources in parallel (max_resources: 2) when both are available.
  • min_experience_level filters the eligible set before assignment (for example, tasks requiring 3 cannot use level-2 resources).
  • If fewer resources are available than requested by max_resources, the task starts with what is available (if at least one eligible resource exists) and continues with reduced effective capacity.

This is the first point in the walkthrough where max_resources is actively overridden above the default (1) to allow multi-resource task execution.

\newpage

Example 6: Full constrained project (final build-up)

This example combines core project fields, risks, uncertainty factors, resource constraints, calendars, absences, and sickness.

project:
  name: "Commerce Platform Upgrade"
  description: "Backend modernization with staged rollout"
  start_date: "2026-05-04"
  confidence_levels: [50, 80, 90, 95]
  hours_per_day: 8
  probability_red_threshold: 0.5
  probability_green_threshold: 0.9

project_risks:
  - id: "risk_vendor"
    name: "Vendor API latency"
    probability: 0.2
    impact: 16
    impact_unit: "hours"

tasks:
  - id: "task_001"
    name: "Architecture design"
    estimate: { low: 16, expected: 24, high: 40 }
    uncertainty_factors:
      team_experience: medium
      technical_complexity: medium

  - id: "task_002"
    name: "Core implementation"
    estimate: { low: 80, expected: 120, high: 180 }
    dependencies: ["task_001"]
    resources: ["alice", "bob", "carol"]
    max_resources: 2
    min_experience_level: 2
    risks:
      - id: "risk_rework"
        name: "Unexpected rework"
        probability: 0.25
        impact: 24
        impact_unit: "hours"
  - id: "task_003"
    name: "Migration"
    estimate: { low: 40, expected: 64, high: 96 }
    dependencies: ["task_002"]
    resources: ["alice"]
    max_resources: 1
    min_experience_level: 3

  - id: "task_004"
    name: "Verification and rollout"
    estimate: { low: 24, expected: 40, high: 64 }
    dependencies: ["task_003"]
    resources: ["alice", "bob", "carol"]
    max_resources: 2

resources:
  - name: "alice"
    calendar: "default"
    availability: 1.0
    experience_level: 3
    productivity_level: 1.1
    sickness_prob: 0.02
    planned_absence: ["2026-05-15"]
  - name: "bob"
    calendar: "default"
    availability: 0.8
    experience_level: 2
    productivity_level: 1.0
    sickness_prob: 0.03
  - name: "carol"
    calendar: "part_time"
    availability: 0.75
    experience_level: 2
    productivity_level: 0.9
    sickness_prob: 0.04
    planned_absence: ["2026-06-01", "2026-06-02"]

calendars:
  - id: "default"
    work_hours_per_day: 8
    work_days: [1, 2, 3, 4, 5]
    holidays: ["2026-05-25"]

  - id: "part_time"
    work_hours_per_day: 6
    work_days: [1, 2, 3, 4]
    holidays: []

Run and export all formats:

mcprojsim validate constrained-full.yaml
mcprojsim simulate constrained-full.yaml \
  --iterations 30000 \
  --seed 42 \
  --table \
  --critical-paths 5 \
  -f json,csv,html \
  -o results/constrained-full

Single-pass vs double-pass assignment

Single-pass automatic assignment (available)

Current constrained scheduling uses deterministic single-pass assignment while respecting dependencies, resource eligibility, calendars, and absences.

You use it by defining top-level resources (and optionally calendars). No extra CLI flag is required.

Double-pass criticality assignment (available)

Double-pass criticality-prioritized scheduling is available via CLI and config.

How it works:

  1. Pass 1 runs greedy scheduling for a subset of iterations to estimate task criticality.
  2. Pass 2 re-runs constrained scheduling using criticality ranking as dispatch priority.
  3. Final summary metrics come from pass 2, with a two-pass traceability delta in CLI and exports.

CLI usage:

mcprojsim simulate constrained-full.yaml --two-pass --pass1-iterations 1500 --seed 42 --table

Config usage:

constrained_scheduling:
  assignment_mode: criticality_two_pass
  pass1_iterations: 1500

Notes:

  • --two-pass overrides config and enables criticality_two_pass for that run.
  • --pass1-iterations is capped to total simulation iterations.
  • If pass1_iterations is small, criticality ranking may be noisy.

\newpage

CLI options most relevant to constrained runs

Use these with mcprojsim simulate:

Option Why it matters for constrained scheduling
-n, --iterations More iterations stabilize constrained diagnostics and tail percentiles
-s, --seed Makes resource/sickness-driven runs reproducible
-c, --config Apply custom uncertainty and output/reporting defaults
--two-pass Enable criticality two-pass constrained scheduling for this run
--pass1-iterations Set pass-1 sample budget for criticality ranking in two-pass mode
--critical-paths Show more critical-path sequences for bottleneck analysis
-t, --table Easier reading of diagnostics and interval tables
-f json,csv,html Export constrained diagnostics to all report channels
-o Keep scenario outputs organized for side-by-side comparison
--target-date Evaluate on-time probability against a concrete deadline

Where to configure constrained behavior

In the project file (primary for constrained scheduling)

  • resources[*].availability
  • resources[*].productivity_level
  • resources[*].experience_level
  • resources[*].calendar
  • resources[*].sickness_prob
  • resources[*].planned_absence
  • calendars[*].work_hours_per_day
  • calendars[*].work_days
  • calendars[*].holidays
  • tasks[*].resources
  • tasks[*].max_resources
  • tasks[*].min_experience_level

In the config file (--config)

Use config files for simulation/reporting defaults and shared stochastic model parameters. They do not replace per-resource sickness probabilities in the project file, but they can now define the shared sickness-duration distribution used by constrained scheduling.

Example:

constrained_scheduling:
  sickness_prob: 0.03
  assignment_mode: criticality_two_pass
  pass1_iterations: 1500

simulation:
  default_iterations: 30000

output:
  critical_path_report_limit: 5
  histogram_bins: 80

staffing:
  effort_percentile: 80

sprint_defaults:
  sickness:
    duration_log_mu: 1.10
    duration_log_sigma: 0.90

constrained_scheduling.assignment_mode supports:

  • greedy_single_pass (default)
  • criticality_two_pass

constrained_scheduling.pass1_iterations controls pass-1 ranking depth when two-pass mode is active.

\newpage